3.6 — Boil-Out of a New Unit
6.
Fill the pressure vessel with clean water until the top of the tubes is covered. Add the cleaning solution and then
fill to the top. The temperature of the water used in the initial fill should be at ambient temperature.
7.
The boiler should then be fired intermittently at a low rate sufficient to hold solution just at the boiling point.
Boil the water for at least five hours. Do not produce steam pressure.
FIGURE 3-4.
Water Capacity and Weights
8.
Allow a small amount of fresh water to enter the boiler to create a slight overflow that will carry off surface
impurities.
9.
Continue the boil and overflow process until the water clears. shut the burner down.
10.
Let the boiler cool to 120º F or less.
11.
Remove handhole plates and wash the waterside surfaces thoroughly using a high pressure water stream.
12.
Inspect the surfaces. If they are not clean, repeat the boil-out.
13.
After closing the handholes and reinstalling the safety or relief valves, fill the boiler and fire it until the water is
heated to at least 180º F to drive off any dissolved gasses, which might otherwise corrode the metal.
The above procedure may be omitted in the case of a unit previously used or known to be internally clean. How-
ever, consideration must be given to the possibility of contaminating materials entering the boiler from the system.
On a steam system, the condensate should be wasted until tests show the elimination of undesirable impurities.
During the period that condensate is wasted, be sure make-up water is treated to prevent an accumulation of
unwanted materials or corrosion.
On a hot water system, chemical cleaning is generally necessary and the entire system should be drained after treat-
ment. Consult your local Cleaver-Brooks authorized representative for recommendations, cleaning compounds,
and application procedures.
Generator Sizes
Water - Gallons
Water - Weight
Normal
Flooded
Normal
Flooded
250 HP
1280
1665
10670
13880
300 HP
1560
2020
13000
16840
350 HP
1855
2410
15465
20090
Be sure to drain the hot water to a safe point of discharge to avoid scalding. Failure to follow these instructions could
result in serious injury or death.
!
Warning
Содержание CBLE
Страница 14: ...xiv 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Страница 48: ...Burner Operation and Control 2 22 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Страница 64: ...Waterside Care and Requirements 3 16 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Страница 72: ...Sequence of Operation 4 8 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Страница 133: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 8 13 8 12 Forced Draft Fan FIGURE 8 3 Forced Draft Fan Mounting...
Страница 158: ...Inspection and Maintenance 8 38 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Страница 165: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 7 9 2 Parts Lists and Drawings 9 2 5 Control Panel...
Страница 166: ...Parts 9 8 750 91 revised 2009 Model CB LE Packaged Boiler Manual Control Panel...
Страница 167: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 9 9 2 Parts Lists and Drawings 9 2 6 Entrance Box...
Страница 168: ...Parts 9 10 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 7 Front Head Electrical...
Страница 169: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 11 9 2 Parts Lists and Drawings 9 2 8 Front Davit...
Страница 170: ...Parts 9 12 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 9 Front Head Insulation...
Страница 171: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 13 9 2 Parts Lists and Drawings 9 2 10 Front Head Linkage...
Страница 174: ...Parts 9 16 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 12 Light Oil Air Piping...
Страница 175: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 17 9 2 Parts Lists and Drawings Light Oil Air Piping...
Страница 176: ...Parts 9 18 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 13 Heavy Oil Air Piping...
Страница 177: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 19 9 2 Parts Lists and Drawings Heavy Oil Air Piping...
Страница 178: ...Parts 9 20 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 14 Heavy OIl Alstrom Heater...
Страница 179: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 21 9 2 Parts Lists and Drawings Heavy OIl Alstrom Heater...
Страница 182: ...Parts 9 24 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 16 IFGR Impeller...
Страница 183: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 25 9 2 Parts Lists and Drawings 9 2 17 Pressure Controls...
Страница 184: ...Parts 9 26 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 18 Temperature Controls...
Страница 185: ...750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 27 9 2 Parts Lists and Drawings 9 2 19 W C Main Aux...
Страница 186: ...Parts 9 28 750 91 revised 2009 Model CB LE Packaged Boiler Manual W C Main Aux...
Страница 188: ...Parts 9 30 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 21 Rear Head Sealing Davit...
Страница 193: ......
Страница 194: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com...