Standard Economizers
1-4
Part No. 750-266
Figure 1.2 - Installation, horizontal flow unit w/floor support
Figure 1.3 - Installation, horizontal flow unit w/ceiling support
Two (2) supported I-beams or channels can be used where larger economizers are being installed. The
exchanger can then be set on the beams and slid to the lower stack and/or stack adapter for final
securing. Position four (4) tie rods (as specified and supplied by others) which can be used to suspend
units depending on upper support.
C-B economizers are designed to support a maximum of 500 lbs stack weight above the economizer.
Structural integrity of the building should be verified (by others) prior to installing an economizer by
suspending from the ceiling.
Содержание C1X Series
Страница 1: ...Economizers 750 266 1 15 CRE CCE C2X C1X Operation Manual...
Страница 2: ......
Страница 6: ...vi NOTES...
Страница 20: ...Standard Economizers 1 14 Part No 750 266 Figure 1 7 Piping with circulating tank BOILER...
Страница 29: ...Condensing Economizers Part No 750 266 2 9 Figure 2 7 Dimension diagram C2X BB...
Страница 33: ...Condensing Economizers Part No 750 266 2 13 Figure 2 9 Single boiler with deaerator...
Страница 34: ...Condensing Economizers 2 14 Part No 750 266 NOTES to Figure 2 9 CONTACT LOCAL CB REPRESENTATIVE IZING...
Страница 36: ...Condensing Economizers 2 16 Part No 750 266 Figure 2 10 Single boiler with deaerator and surge tank...
Страница 38: ...Condensing Economizers 2 18 Part No 750 266 2 4 3 Two boilers with deaerator refer to Figure 2 11...
Страница 39: ...Condensing Economizers Part No 750 266 2 19 Figure 2 11 Two boilers with deaerator...
Страница 40: ...Condensing Economizers 2 20 Part No 750 266 NOTES to Figure 2 11 CONTACT LOCAL CB REPRESENTATIVE IZING...
Страница 42: ...Condensing Economizers 2 22 Part No 750 266 Figure 2 12 Two boilers with deaerator and surge tank...
Страница 51: ...Condensing Economizers Part No 750 266 2 31...
Страница 52: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com...