Install anchors into the floor. Replace raise floor panels and insert
threaded rods through the four holes.
Note:
You are not installing the rods at this point. We are measuring
the rods to be cut to the appropriate length.
Measure the rods 2.5” above the floor and mark with a permanent
marker. Remove the rods and cut each rod at the mark. Remove
the floor panels.
Before installing rods back into the floor, place a nut and then a
washer on the threaded rods. Take the rod and install it into the
anchor installed in the floor.
Tighten the nut down to secure the rod into the floor. Tighten each
bolt to 65 ft-lbs., +10, -0 ft-lbs. The anchor will expand and secure
itself to the floor.
Once all four rods are secure, thread another hex nut, then washer
on each rod. Make sure the nut and washer are approximately ½”
below the raised floor level. This hardware will be tightened down
AFTER the frame is set into place but BEFORE securely bolting the
frame to the floor.