Step 10
Store the pallet and packaging material for future use if you have to ship the empty Cisco R42612 rack cabinet.
Step 11
Make sure that the location where the rack will be installed has the required power and meets the description
detailed
Step 12
Verify that the doors that you must pass through on the way to the installation location can accommodate the
width and height of the Cisco R42612 rack on its wheels.
Step 13
Verify that the flooring ready.
Step 14
Roll the rack to the location where it will be installed.
Cisco R42612 Rack and RP-Series Metered Input PDU Installation Guide
26
Unpacking the Rack
Removing the Cisco Cisco R42612 Rack from the Pallet