5. Click OK to complete the NIC teaming configuration. It may take a few minutes to complete after you click OK.
To verify that the vPC is formed, go to one of the Cisco Nexus 5000 Series Switches to check the status of the
server PortChannel interface. Since the pair of Cisco Nexus 5000 Series Switches is in a vPC configuration, they
each have a single port in the PortChannel. Checking the status of the PortChannel on each parent switch shows
that channel group 201 is in the “P - Up in port-channel” state on each switch. A check from the HP Network
Configuration Utility will show the status “Available” for each link that is up in the PortChannel.
5548-Bottom# show port-channel summary
Flags: D - Down P - Up in port-channel (members)
I - Individual H - Hot-standby (LACP only)
s - Suspended r - Module-removed
S - Switched R - Routed
U - Up (port-channel)
-------------------------------------------------------------------------------
Group Port- Type Protocol Member Ports
Channel
-------------------------------------------------------------------------------
20 Po20(SU) Eth NONE Eth1/9(P) Eth1/10(P)
103 Po103(SU) Eth NONE Eth1/1(P) Eth1/2(P)
201 Po201(SU) Eth LACP Eth103/1/1(P)
5548-Bottom #
N5548-Top# show port-channel summary
Flags: D - Down P - Up in port-channel (members)
I - Individual H - Hot-standby (LACP only)
s - Suspended r - Module-removed
S - Switched R - Routed
U - Up (port-channel)