Verification Time and Date
Planning Activity
Power evaluation:
Input power type
Power receptacles
Receptacle proximity to the
equipment
Dedicated (separate)
circuits for power
redundancy
UPS for power failures
Grounding: proper wire
gauge and lugs
Circuit breaker size
Grounding evaluation:
Data center ground
Cable and interface equipment
evaluation:
Cable type
Connector type
Cable distance limitations
Interface equipment
(transceivers)
EMI evaluation:
Distance limitations for
signaling
Site wiring
RFI levels
Contact and Site Information
Use the following worksheet to record contact and site information
Contact person
Contact phone
Cisco Nexus 7706 Hardware Installation Guide
OL-31330-01
172
Site Preparation and Maintenance Records
Contact and Site Information
Содержание Nexus 7706
Страница 8: ...Cisco Nexus 7706 Hardware Installation Guide OL 31330 01 viii Contents ...
Страница 26: ...Cisco Nexus 7706 Hardware Installation Guide OL 31330 01 14 Preparing the Site Clearance Requirements ...
Страница 170: ...Cisco Nexus 7706 Hardware Installation Guide OL 31330 01 158 Switch Specifications Switch Specifications ...
Страница 178: ...Cisco Nexus 7706 Hardware Installation Guide OL 31330 01 166 LEDs Power Supply LEDs ...
Страница 190: ...Cisco Nexus 7706 Hardware Installation Guide OL 31330 01 IN 4 INDEX ...