7-34
Network Processing Engine and Network Services Engine Installation and Configuration
OL-4448-12
Chapter 7 NPE-G1 and NPE-G2 Installation and Configuration Information
Installing the NPE-G1 or NPE-G2
You have finished installing the cable-management brackets. Go to the
“Reconnecting Input Power and
Powering Up the Router” section on page 7-35
.
Installing the Default Cable-Management Bracket on a Cisco uBR7246VXR Router (Optional)
If you are not using the NPE-G1 cable-management bracket, you can alternatively use two
cable-management bracket configurations for the Cisco uBR7246VXR router. In the first configuration,
for a 4-post rack, the rack-mount brackets are installed at the rear of the chassis and the
cable-management bracket is installed at the right front of the chassis. (See
Figure 7-22
.) You must
install both sets of brackets before you install the chassis in the rack.
In the second configuration, for a telco-type rack, the rack-mount brackets are installed at the middle of
the chassis and the cable-management bracket is installed at the right front of the chassis. (See
Figure 7-23
.) You must install both sets of brackets before you install the chassis in the rack.
Note
The cable-management bracket must be installed on the right side of the chassis when viewed from the
front.
Figure 7-22
Installing the Chassis in a 4-Post Rack with an Installed Cable-Management Bracket
1
Rack-mount bracket
2
Cable-management bracket
93812
1
2