Wiring
8
Load / Solar Balancing Probe
9
After the device has been fixed to wall or pole it’s time for wiring to
the electrical line, the device it’s equipped with 1 meter connetion
cable and , as stated before, has to be equiped with protection device.
Connect EARTH (yellow/green) - NEUTRAL (blue) - L1 (brown) if 1P
Connect EARTH (yellow/green) - NEUTRAL (blue) - L1 (brown) - L2
(black) - L3 (gray)
Device it’s equipped with load / Solar balancing probe for automatic energy management. Only
one option per time can be active. Probe is connected to chargepoint via lower 3.5mm Jack
connector
SOLAR BALANCING: Install the probe on Hybrid inverter AC output to catch the exceeding AC
production from solar
LOAD BALANCING: install the probe to catch energy consumption of the house excluded
charger.
IMPORTANT: For a correct installation ONLY phases cables ( L1,L2,L3) must pass through the
probe. NOT NEUTRAL. in case of 3 phase only 1 cable has to pass trought the current probe. The
calculation is made by multiply by 3 the value of single line so a balanced between line load/
solar generation is required for a correct work