5.0 Maintenance 

 
5.1 Introduction 

 

The 

CBS  ArcSafe® 

RRS-2  is  designed  to  require  little  maintenance;  however,  adopting  a  regular 

maintenance program will keep the RRS-2 in good condition allowing years of trouble-free service. 
 

5.2 Prior to Use

 

 

Before use examine the general condition of the unit. 
 

1.

 

Inspect the switch and indicators for tightness and damage.   

2.

 

Inspect the cables for wear or cracking, always replace a damaged cable. 

3.

 

Check cable core grips for tightness. 

4.

 

Check for loose fasteners. 

5.

 

Ensure  actuators  are  free  of  dirt  and  grime  by  wiping  down  with  a  dry 
cloth. 

6.

 

Run the unit unloaded to verify there is no abnormal noise or vibration.  If 
abnormal condition exists, do not use. 

7.

 

If  the  unit  has  been  inactive  for  more  than  30  days,  please  measure  the 
voltage across each battery in order to ensure that they are both running at 
12Vdc for a combined 24Vdc 

 

5.3 After Use

 

 

After use, clean the RRS-2 ensuring the power supply vents are free of dust and debris. Ensure the unit is 
free  of  oil  or  grease  and  if  necessary,  clean  with  a  dry  cloth.    Store  the  device  covered  with  either  the 
standard dust cover or the waterproof cover (optional), in a clean, dry location to prevent damage. 
 
 

5.4 Every 12 to 18 Months

 

 

Every twelve to eighteen months, depending on use, 

CBS ArcSafe®

 recommends performing the following 

preventative maintenance.  
 

1.

 

Check that the batteries maintain a charge. 

 

2.

 

Perform  an  electrical  inspection  of  internal  wiring,  checking  for  signs  of 
heat and loose connections. 

 

3.

 

Check all cables for extreme wear or cracks. 

 

4.

 

Check  that  the  pneumatic  tires  (optional)  are  properly  pressurized  to  24 
PSI and sufficiently sealed. 
 

 

Содержание RRS-2

Страница 1: ...RRS 2 Technical Manual P O Box 550 Argyle TX 76226 940 382 4411 www CBS ArcSafe com Remote Racking System CBS ArcSafe...

Страница 2: ...on Remote Racking System The RRS 3 system is an inexpensive single application remote racking system which allows the operator to install and remove a breaker while standing 25 to 75 feet away with a...

Страница 3: ...RS 2 for Operation 14 3 6 Current Control Module CCM Configuration 15 3 6 1 Manual Current Control Configuration 15 3 6 2 Automatic Current Control Configuration 17 3 6 2 Automatic Current Control Tim...

Страница 4: ...Options 27 Appendix B Troubleshooting Guide 29 Appendix C Wireless Camera System 31 1 0 Components 31 2 0 Camera System Set up 32 3 0 Camera System Operation 32 4 0 Camera Troubleshooting Guide 33 Ap...

Страница 5: ...user will want to pay particular attention to DANGER Ensure that personnel using this equipment are adequately trained in the operation of the switchgear they are planning to work with that they are...

Страница 6: ...slide rail is an extruded aluminum track system allowing for the quick repositioning of the cubicle brace and actuator assembly Several optional slide rail configurations are available including sing...

Страница 7: ...ndant Station 2 Steel Frame 5 Main Actuator 8 Control Cabinet 3 Slide Rail Locks 6 Cubicle Brace 9 Transportation and Stability Wheels 1 1 2 2 3 3 4 5 6 7 8 9 Figure 1 1 Structural Assembly Floor Lock...

Страница 8: ...be equipped with stair climber rails optional Floor Locks and Stabilizers optional 1 2 The RRS 2 may be equipped with optional floor locks or stabilizers Engaging the floor locks lifts the transporta...

Страница 9: ...RRS 2 Technical Manual 5 2010 CBS ArcSafe 2012 04 18 Figure 1 3 RRS 2 Stair Climber Rails optional Figure 1 4 RRS 2 Pneumatic Tires optional...

Страница 10: ...ernal Figure 1 5 Interlock Actuators and Tooling ATTENTION These are only two interlock actuators and tooling of many designs that are available Every RRS 2 tooling accessory is custom built for your...

Страница 11: ...If the operator cannot leave the arcflash area with the length of the cable we offer extension cables radio remote pendant stations and wireless video systems to ensure that the operator can be as far...

Страница 12: ...of the power switch Main Linear Actuator Port Fig 2 1 5 The main linear actuator port provides power for the main racking functions of the RRS 2 when the main linear actuator cable is properly connect...

Страница 13: ...8 MODEL RSS 1 Distance is Safety UP INSTALL REMOVE DOWN MAX CURRENT www CBS ArcSafe com 800 L ON I G H T S OFF C ON A M E R A OFF Figure 2 1 RRS 2 Electrical Cabinet Mounted Controls 1 2 3 4 5 6 7 8 l...

Страница 14: ...ion This section lists the preliminary steps for operation 3 3 Charging the RRS 2 This section describes the procedure for charging the remote racking system to prepare it for future operations 3 6 Cu...

Страница 15: ...e already received the proper training 1 Remove the cardboard cover by cutting the perimeter at the base with a utility knife or removing the nails screws 2 Carefully remove the steel strapping that s...

Страница 16: ...use the RRS 2 in normal operation mode 4 Whenever possible leave the CBS ArcSafe RRS 2 plugged in and properly stowed with either the CBS ArcSafe dust cover or the waterproof cover to ensure the RRS...

Страница 17: ...djustable by Philips head screwdriver 1 Loosen the two screws with a Philips head screwdriver 2 Position the limit switches as desired these switches determine how the actuator extends and retracts 3...

Страница 18: ...fications 3 Position the remote racking system in front of the circuit breaker to be racked with the cubicle brace aligned with the circuit breaker cubicle 4 Ensure the safety shut off switch on the p...

Страница 19: ...wing steps to set the current control limit settings to 0 0 amps 1 Ensure that the RRS 2 has been properly set up for operation 2 With the main power switch ON press and hold the install remove trip p...

Страница 20: ...uit breaker and stowed a Rewind the pendant retractile cord and return the pendant station to the storage hooks b Disengage the foot brakes if engaged c Remove the circuit breaker racking adapter and...

Страница 21: ...own Max Current button before running the RRS 2 the internal memory of the current control module will retain the largest current values reached during operation To reset turn the Max Current function...

Страница 22: ...pendant station to the storage hooks provided a Remove the circuit breaker racking adapter and any extensions from the breaker and RRS b Switch the power isolation switch to the OFF position c Cover...

Страница 23: ...unt before turning off anywhere from 0 seconds to 9 seconds in increments of 1 seconds for versions 2 4 or newer To set the Time Stop follow the following instructions 1 Press both the Install and Rem...

Страница 24: ...nes at ALL times DANGER Remove control power from the control circuit if applicable in order to prevent the accidental closing or tripping of the breaker during the racking procedure 4 1 2 Steps for I...

Страница 25: ...to the breaker using the breaker specific tooling provided 3 Verify the circuit breaker is OPEN according to manufacturer specifications and company safety policies 4 Exit the arc flash boundary with...

Страница 26: ...7 If the unit has been inactive for more than 30 days please measure the voltage across each battery in order to ensure that they are both running at 12Vdc for a combined 24Vdc 5 3 After Use After us...

Страница 27: ...23 2010 CBS ArcSafe 2012 04 18 6 0 Ordering Replacement Parts When ordering replacement parts please specify the serial number and MFD from the RRS 2 nameplate From the RRS 2 nameplate Nomenclature R...

Страница 28: ...nual 24 2010 CBS ArcSafe 2012 04 18 Remote Racking Unit RRS 2 Parts List Item Description CBS ArcSafe Part Image 1 2 12Vdc Batteries for 24 Vdc 2 Battery Charger 3 Power Cable 4 Charging Light 5 Front...

Страница 29: ...e 2012 04 18 Remote Racking Unit RRS 2 Parts List Cont Item Description CBS ArcSafe Part Image 7 25 Pendant Retractile Cord Extension optional 8 Power Switch 9 Power Light 10 Storage Bag 11 PS mounted...

Страница 30: ...RS 2 Technical Manual 26 2010 CBS ArcSafe 2012 04 18 Remote Racking Unit RRS 2 Parts List Cont Item Description CBS ArcSafe Part Image 13 Standard Tires 14 Pneumatic Tires Recommended for rough terrai...

Страница 31: ...an be viewed remotely Radio Remote Pendant Station The radio remote pendant station allows for the operator to control the RRS 2 remotely without needing to be tethered to the RRS 2 High Lift The high...

Страница 32: ...RRS 2 Technical Manual 28 2010 CBS ArcSafe 2012 04 18 This page has been intentionally left blank...

Страница 33: ...ill not hold a charge The battery leads are disconnected The battery charger is not connected to AC power Faulty batteries or charger The RRS 2 has been stored in freezing temperatures The batteries h...

Страница 34: ...RRS 2 Technical Manual 30 2010 CBS ArcSafe 2012 04 18 This page has been intentionally left blank...

Страница 35: ...er cable and internal battery pack Wireless Video Receiver The wireless video receiver is inside of the monitor pack and has multiple channels for combating wireless interference LCD Display The LCD d...

Страница 36: ...less signal 3 0 Camera System Operation The system is operated in the following manner 1 Charge the LCD display a The initial charge was performed by CBS ArcSafe personnel subsequent charges are perfo...

Страница 37: ...align wireless system antennas No video signal Check to ensure the camera is connected to the racking unit Check to ensure the CAMERA switch is ON Check to ensure that the camera and receiver are on t...

Страница 38: ...RRS 2 Technical Manual 34 2009 CBS ArcSafe 2012 04 18 This page has been intentionally left blank...

Страница 39: ...ease keep the radio remote with the system that it came with Also to limit interference please ensure that the channel numbers of units purchased at different dates differ Radio Remote Receiver The ra...

Страница 40: ...please ensure that the pendant station is turned on before troubleshooting why the power in your system is not turning on PS R6 Fig D 1 3 The PS R6 radio remote has six control buttons that are design...

Страница 41: ...RRS 2 Technical Manual 37 2009 CBS ArcSafe 2012 04 18 3 0 Button Configurations Figure D 2 Possible Button Configurations REMOVE A REMOVE A B INSTALL A B INSTALL A REMOVE B INSTALL B PS R6 C...

Страница 42: ...RRS 2 Technical Manual 38 2009 CBS ArcSafe 2012 04 18 This page has been intentionally left blank...

Страница 43: ...adio remotes are NOT interchangeable between systems and are unique for every system Replace the 2 AA batteries inside of the remote This may require you removing the remote from its protective plasti...

Страница 44: ...protective equipment PPE Guarantee Equipment is guaranteed free of inherent electrical or mechanical defects for one 1 year from date of shipment and to perform according to ratings under normal cond...

Страница 45: ...form as soon as possible Date CBS ArcSafe Model CIRCLE ONE RRS 2 RRS 2 BE CBS ArcSafe Serial Number Company Address 1 Address 2 City State Province Zip Postal Code Country Telephone and Fax Contact Pe...

Отзывы: