![Calimet CM7-ACFP Скачать руководство пользователя страница 3](http://html1.mh-extra.com/html/calimet/cm7-acfp/cm7-acfp_instruction-manual_3450221003.webp)
Installation
1. Lay out position of 6 wedge anchors by measuring clearance between anchors
and inside edge of gate. Figure 1
2. Install underground conduits in area for conduits. Figure 2
Wedge Anchor
Step
1
:
Install
ing the
Base
The base, also known as a pad is a raised platform. We recommend using a concrete base.
1/2" x 3 1/2"
2
Contact local underground utility locating companies before digging more than 12 inches deep to
avoid damaging underound power, gas or other utulity lines.
Size of concrete base
A minimum of 2" on each side of the operator is recommended.