System Checking
No. ITEM
YES
NO
Before Turning on the system
1
No parts from delivery (Scope of delivery) is missing
2
No parts delivered is damaged or failed.
3
The grid power is Off
4
The switch of PDU is Off
5
It passed Insulation resistance test and puncture test.
6
Visual if all grounding points is grounded correctly, and matches the
installation manual.
7
Visual check if all power cables position matches with the installation manual
and each labels (See figure in Chapter 7.1)
8
Visual check if the communication cables position matches with the
installation manual and each labels. (See figure 7.1)
9
Checked every torque and marks on every connection points.
10
All components are in connection box is installed and connected.
Post turning on the system
If any of these items is checked as “NO”. Turn off the PDU switch first. Then press the power button on PDU. If
needed, turn off the AC power.
11
The PDU indicator is on GREEN Light, No RED light
12
The meter is connected.
13
The inverter is on non-error status.
14
Check battery Info via BMS software
Test.
Puncture
Test
Grounding Point
BAT+
Grounding Point
QLI-3
Grounding Point
QLI-2
Grounding Point
BATT-
Puncture
Test
OUT+
OUT-
BAT+
QLI-2
BAT-
QLI-3
Grounding
Impedance
Grounding Rail
PDU cover
Grounding Rail
Metal frame cabinet 1
Grounding Rail
Metal frame cabinet 2
Grounding Rail
Metal frame cabinet 3
Grounding Rail
Metal frame inverter cabinet
Содержание Battery-Box C130
Страница 1: ...English Version1 1 Battery Box C130 Installation Manual ...
Страница 14: ...11 Copyright BYD Europe B V all rights reserved Figure1 Installation Space ...
Страница 27: ...24 Copyright BYD Europe B V all rights reserved Figure14 Figure10 1 Figure11 2 Figure12 3 Figure13 4 ...
Страница 41: ...38 Copyright BYD Europe B V all rights reserved Figure42 Figure43 ...