Figure 4: Supply Water Manifold Piping
Install pipe tee between circulator and boiler return
along with second tee in supply piping as shown in
Figure 25 or 26. Bypass should be same size as the
supply and return lines with valves located in bypass
and supply outlet as illustrated in Figure 25 or 26 in
order to regulate water flow to maintain higher boiler
water temperatures.
After the boiler is operational (reference Section VIII.
System Start-Up) set by-pass and boiler supply valves
to half throttle position to start. Operate boiler until
system water temperature reaches normal operating
range.
Adjust valves to provide 180° to 200°F supply water
temperature. Opening the boiler supply valve will raise
system temperature, while opening the by-pass valve
will lower system supply temperature.
J.
A hot water boiler installed above radiation level
must be provided with a low water cutoff device as part
of installation.
K
.
If a low water cutoff is required,
it must be mounted
in the system piping above the boiler. The minimum
safe water level of a hot water boiler is just above the
highest water containing cavity of the boiler; that is, a
hot water boiler must be full of water to operate safely.
L.
Oil, grease, and other foreign materials
which
accumulate in new hot water boilers and a new
or reworked system should be boiled out, and
then thoroughly flushed. A local qualified water
treatment chemical specialist is a suggested source
for recommendations regarding appropriate chemical
compounds and concentrations which are compatible
with local environmental regulations.
M.
After the boiler and system have been cleaned and
flushed,
and before refilling the entire system add
appropriate water treatment chemicals, if necessary, to
bring the pH between 7 and 11.
N.
If it is required to perform a long term pressure
test of the hydronic system
, the boiler should first be
isolated to avoid a pressure loss due to the escape of air
trapped in the boiler.
To perform a long term pressure test including the
boiler, ALL trapped air must first be removed from the
boiler.
A loss of pressure during such a test, with no visible
water leakage, is an indication that the boiler contained
trapped air.
Содержание SCG
Страница 5: ...Figure 2 Dimensions...
Страница 13: ...13 Figure 4A Recommended Separate Horizontal Vent Air Intake Installation...
Страница 14: ...14 Figure 4B Alternate Separate Horizontal Vent Air Intake Installation...
Страница 15: ...15 Figure 5A Separate Horizontal Vent Air Intake Terminal Configuration SCG 3 thru 7...
Страница 16: ...16 Figure 5B Separate Horizontal Vent Air Intake Terminal Configuration SCG 8 and 9...
Страница 19: ...19 Figure 7 Attic Offset Figure 6 Vertical Vent Installation...
Страница 22: ...22 Figure 9 Vertical Air Intake Piping...
Страница 25: ...25 Figure 10 Combination Horizontal Vent Air Installation SCG 3 thru 6...
Страница 26: ...26 Figure 11 Combination Horizontal Vent Air Terminal Installation SCG 3 thru 6...
Страница 38: ...38 Figure 12 Recommended Separate Horizontal Vent Installation...
Страница 39: ...39 Figure 13 Alternate Separate Horizontal Vent Installation...
Страница 44: ...44 Figure 22 Optional Separate Horizontal 4 Vent Terminal Installation Indoor Air...
Страница 48: ...48 Figure 25 Recommended Water Piping for Circulator Zoned Heating Systems...
Страница 49: ...49 Figure 26 Recommended Water Piping for Zone Valve Zoned Heating Systems...
Страница 54: ...54 Figure 28 Internal Boiler Wiring Schematic Diagram...
Страница 57: ...57 Figure 30 System Wiring Schematic for Single Zone Space Heating Only...
Страница 59: ...59 Figure 32 Circulator Zoned System Wiring Schematic...
Страница 60: ...60 Figure 33 Zone Valve Zoned System Wiring Schematic...
Страница 61: ...61 Figure 34 Different Manufacturer s Zone Valve Connections to Honeywell R8889...
Страница 63: ...63 Figure 35 Modular Boiler Gas Piping...
Страница 65: ...65 Figure 36 Operating Instructions...
Страница 68: ...68 Figure 38 Troubleshooting Guide Honeywell Electronic Ignition Troubleshooting Guide...
Страница 73: ...73 Figure 44 Flue and Burner Cleanout 1 Burner...
Страница 75: ...75 THIS PAGE LEFT INTENTIONALLY BLANK...
Страница 76: ...76...
Страница 77: ...77...
Страница 80: ...80...
Страница 82: ...82...
Страница 84: ...84...
Страница 86: ...86...
Страница 88: ...88...
Страница 90: ...90...
Страница 94: ...94 SERVICE RECORD DATE SERVICE PERFORMED...
Страница 95: ...95 SERVICE RECORD DATE SERVICE PERFORMED...