Installation / Service / User Manual
BURNERTECH
12
4 Commissioning
NOTICE
All Inverterjet premix burners are test fired in the factory prior to despatch to the customer.
Whenever possible, Burnertech prefer to pre-set the maximum and minimum fan speed to assist
the commissioning process
In order to ensure maximum product reliability, we advise and request that a Burnertech
approved engineer conduct the 1st burner commissioning. Failure to comply with this
requirement may result to inappropriate burner setting which can lead to damage to property and
injuries to personnel.
4.1
Commissioning procedure
To start the commissioning procedure, follow the steps bellow:
1. Connect a Manometer to the gas inlet pressure test nipple on the burner gas inlet
connection.
2. Locate CO/CO
2
combustion analyser into flue pipe as close as possible to the appliance
outlet.
3. Confirm and record that adequate ventilation is available for the safe operation of the
burners.
4. Establish that the system pipe work is complete, fully purged and adequate system load
and circulation exists to facilitate firing of the burners.
5.
Turn ‘On’ the gas supply and ensure adequate static gas pressure is available at the burner
inlet.
6. Locate the position of the Throttle adjustment screw (High rate throttle adjuster)
7.
Locate the position of the Offset adjustment screw (Low rate offset adjuster).
1 Throttle Adjustment Screw
2 Offset Adjustment Screw
3 Reset Button
4
Indicator Light (Alarm)
Содержание INVERTERJET 30M/L
Страница 4: ...Installation Service User Manual BURNERTECH 3...
Страница 8: ...Installation Service User Manual BURNERTECH 7 3 Installation 3 1 General Installation Information...
Страница 17: ...Installation Service User Manual BURNERTECH 16 5 User Instructions 5 1 Limitations on use of Burner...
Страница 22: ...Installation Service User Manual BURNERTECH 21 6 3 2 Maintenance Notes...
Страница 23: ...Installation Service User Manual BURNERTECH 22...