Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
CL-2
Replaces: SM581J-17-28-01
© 2019 Bryant Heating & Cooling Systems
Cat. No. 04-53581021-01
Edition Date: 12-19
Printed in U.S.A
Form No: SM581J-17-28-02
TEMPERATURES
Outdoor-air Temperature
_____________ °F DB (Dry Bulb)
Return-air Temperature
_____________ °F DB
_____________
°
F Wb (Wet Bulb)
Cooling Supply Air Temperature
_____________ °F
Gas Heat Supply Air Temperature
_____________ °F
PRESSURES
Gas Inlet Pressure
_____________IN. WG
Gas Manifold Pressure
STAGE 1
_____________IN. WG
STAGE 2
_____________IN. WG
Refrigerant Suction
CIRCUIT A _____________ PSIG
_____________ °F
CIRCUIT B _____________ PSIG
_____________ °F
Refrigerant Discharge
CIRCUIT A _____________ PSIG
_____________ °F
CIRCUIT B _____________ PSIG
_____________ °F
Verify Refrigerant Charge using Charging Charts (Y/N) _____
Verify that 3-phase fan motor and blower are rotating in the correct direction (Y/N) _____
Verify that 3-phase scroll compressor is rotating in the correction direction (Y/N) _____
GENERAL
Economizer minimum vent and changeover settings to job requirements (if equipped) (Y/N) _____
Verify smoke detector unit shutdown by utilizing magnet test (Y/N) _____
IV. PERFECT HUMIDITY START-UP
NOTE: Units equipped with RTU Open controls have Service Test menus or modes that can assist with the Perfect Humidity System Start-Up
function and provide the means to make the observations listed for this start-up.
STEPS
1. Check CTB for jumper 5, 6, 7 (Jumper 5, 6, 7 must be cut and open) (Y/N) _____
2. Open humidistat contacts (Y/N) _____
3. Start unit In cooling (Close Y1) (Y/N) _____
OBSERVE AND RECORD
A. Suction pressure
_______________ PSIG
B. Discharge pressure
_______________ PSIG
C. Entering air temperature
_______________ ° F
D. Liquid line temperature at outlet or reheat coil
_______________ ° F
E. Confirm correct rotation for compressor (Y/N) _____
F. Check for correct ramp-up of outdoor fan motor as condenser coil warms (Y/N) _____
4. Check unit charge per charging chart (Y/N) _____
(Jumper 32L Motormaster
®
temperature sensor during this check. Remove jumper when complete.)
5. Switch unit to high-latent mode (sub-cooler) by closing humidistat with Y1 closed (Y/N) _____
OBSERVE
A. Reduction in suction pressure (5 to 7 psi expected) (Y/N) _____
B. Discharge pressure unchanged (Y/N) _____
C. Liquid temperature drops to 50°F to 55°F range (Y/N) _____
D. LSV solenoid energized (valve closes) (Y/N) _____
6. Switch unit to dehumid (reheat) by opening Y1 (Y/N) _____
OBSERVE
A. Suction pressure increases to normal cooling level
B. Discharge pressure decreases (35 to 50 psi) (Limited by Motormaster control)
C. Liquid temperature returns to normal cooling level
D. LSV solenoid energized (valve closes)
E. DSV solenoid energized, valve opens
7. With unit in dehumid mode close W1 compressor and outdoor fan stop; LSV and DSV solenoids de-energized
(Y/N) _____
8. Open W1 restore unit to dehumid mode (Y/N) _____
9. Open humidistat input compressor and outdoor fan stop; LSV and DSV solenoids de-energized (Y/N) _____
10. Restore set-points for thermostat and humidistat (Y/N) _____
REPEAT PROCESS FOR 2 COMPRESSOR SYSTEMS.
Содержание 581J 17-28 Series
Страница 18: ...18 COOLING CHARGING CHARTS Fig 21 Cooling Charging Chart 15 Ton ...
Страница 19: ...19 Fig 22 Cooling Charging Chart 17 5 Ton ...
Страница 20: ...20 Fig 23 Cooling Charging Chart 20 Ton ...
Страница 21: ...21 Fig 24 Cooling Charging Chart 25 Ton ...
Страница 36: ...36 Fig 47 Unit Control Box IGC Location IGC Board IGC Board Side view Front view ...
Страница 39: ...39 Fig 50 Integrated Gas Control IGC Board RED LED STATUS ...
Страница 45: ...45 Fig 56 RTU Open Overlay for Economizer Wiring ...
Страница 46: ...46 Fig 57 VFD Overlay for W2770 Controller Wiring ...
Страница 84: ...84 Fig B 581J 17 28 Control Diagram 208 230 3 60 460 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 85: ...85 Fig C 581J 17 28 Power Diagram 208 230 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 86: ...86 Fig D 581J 17 28 Power Diagram 460 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 87: ...87 Fig E 581J 17 28 Power Diagram 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 88: ...88 Fig F 581J 17 28 Control Diagram with Perfect Humidity System APPENDIX D WIRING DIAGRAMS ...
Страница 89: ...89 Fig G 581J 17 28 Power Diagram 208 230 3 60 with Perfect Humidity System APPENDIX D WIRING DIAGRAMS ...
Страница 90: ...90 Fig H 581J 17 28 Power Diagram 460 3 60 with Perfect Humidity System APPENDIX D WIRING DIAGRAMS ...
Страница 91: ...91 Fig I 581J 17 28 Power Diagram 575 3 60 with Perfect Humidity System APPENDIX D WIRING DIAGRAMS ...
Страница 92: ...92 Fig J RTU OPEN Wiring Diagram APPENDIX D WIRING DIAGRAMS ...
Страница 93: ...93 Fig K RTU OPEN Wiring Diagram with Perfect Humidity System APPENDIX D WIRING DIAGRAMS ...