26.

 

Edit the interface in BruControl’s Settings (gear icon). Change the IP address to match 
the UniFlex’s IP address above. The Status should change from a red X to a green 
checkmark, indicating the UniFlex is connected to BruControl. 

 

UniFlex Power & Accessories 

27.

 

Once the above steps have been completed successfully, continue to connect brewery 

devices via the steps below.  

28.

 

Ensure the UniFlex is powered down via the Power Button. 

29.

 

Plug in vessel device(s) (e.g., vessel heating elements). These will have L6-30P locking 

plugs and will connect to the UniFlex L6-30R vessel power output receptacle(s). Fully 

insert and turn the plug into the receptacle to ensure it is locked and properly 

connected. When looking at the back of the UniFlex, the pigtail cable for vessel power 

output #1 is on the right is #1 and #2 (if dual vessel equipped) is on the left.  

30.

 

Plug in accessory device(s) (e.g., pumps). These will have 5-15P plugs and will connect to 

the UniFlex 5-15R accessory power output receptacle(s). Fully insert the plug into the 

receptacle to ensure it is properly connected. When looking at the back of the UniFlex, 

the pigtail cable for accessory power output #1 is on the right is #1 and #2 (if dual 

accessory equipped) is on the left. 

31.

 

Plug in the Input Power Plug into the appropriate 240VAC GFCI protected source. 

 

Initial Testing 

32.

 

Prior to connecting and testing vessel devices (Mash Tun, Hot Liquor Tank, Boil Kettle 

RIMs tube, etc.), it is highly recommended to fill all vessels with water. This will ensure 

that activation of the heating elements does not incur damage. 

33.

 

Power on the UniFlex via the front power switch and ensure that BruControl application 

reports it as connected. 

34.

 

Enable the UniFlex Device Elements to test functionality. First, enable the Vessel 

Temperature Device Element(s). They should report a temperature(s). 

a.

 

The temperature probes index on startup. The first time a system is used, or 

when probes are changed, the indexing order may need to be updated. 

b.

 

Temporarily touch the tip of each probe to heat it slightly, then identify which 

Vessel Temp Device Element in the Workspace is responding. If the incorrect 

Element is responding, the desired Element’s index number should be changed 

to the one which actually showed the temperature response. For example, if 

Vessel 1 has an index of 0 and Vessel 2 has an index of 1, and the probe inside 

Vessel 1 causes the reading of Vessel 2 to respond, Vessel 1’s index should be 

changed to 1. 

35.

 

Enable the ‘Element Interlock’ Device Element. A click sound from the relay(s) inside 

should be heard. Selecting it to switch elements (if equipped) should result in two 

concurrent click sounds. 

36.

 

Enable the Pump (accessory) Device Element(s) and select them to turn them ON. The 

connected accessory(s) should run appropriately. 

37.

 

If the Vessel Power devices (heating elements) are in a condition they can be powered 

(e.g., under liquid), enable the Duty Cycle Device Element and set its output to 100% to 

Содержание UF-1

Страница 1: ...t internal cooling option and plug and play temperature probes The UniFlex is built on a foundation of BruControl technology and integrates into the BruControl application s ecosphere The UniFlex s co...

Страница 2: ...the specifications listed below For example exceeding the specified current limits may cause damage to the unit or associated equipment Do not use the UniFlex for any application other than its inten...

Страница 3: ...s the distal end of the temperature probes Warning This product contains or may contain chemical s known to the State of California to cause cancer birth defects or other reproductive harm Specificati...

Страница 4: ...and use shielded cable for noise reduction o 1 wire technology allows for up to 10 probes simultaneously plugged in requires separate adapter not included o 1 probe included with single vessel contro...

Страница 5: ...h dual feed power NEMA 6 30P and 5 15P plugs UF 1 L6D Single Vessel 30A with dual feed power NEMA L6 30P and 5 15P plugs UF 1 10D Single Vessel 30A with dual feed power NEMA 10 30P and 5 15P plugs Uni...

Страница 6: ...Front Panel v1 A Power Button green LED B I O Power Connector option C I O Connector option D Temperature Probe Jack s E Wi Fi Antenna jack antenna Front Panel v2 A Power Button blue LED B I O Connect...

Страница 7: ...ear Panel A 240VAC Power Input B Vessel Power Output 1 if Dual Feed power model C Vessel Power Output 2 option D 120VAC Power Input excluded on NEMA 14 30P single feed units E Pump Accessory Power Out...

Страница 8: ...al vessel equipped G PID Control H Duty Control Initial Set Up Unpacking 1 Carefully unpack the UniFlex taking precautions not to place any undue stress on the cables by torquing pushing or pulling on...

Страница 9: ...etup mode following power on Therefore do not plug anything including the 5 port splitter during this process 9 Power on the UniFlex via the Power Button Ensure the button glows green v1 or blue v2 an...

Страница 10: ...uControlUniFlex 19 Download and unzip extract the UniFlex Images file BruControlUniflex zip into the folder made in the step above There should be nine image files there now which can be moved later i...

Страница 11: ...es Mash Tun Hot Liquor Tank Boil Kettle RIMs tube etc it is highly recommended to fill all vessels with water This will ensure that activation of the heating elements does not incur damage 33 Power on...

Страница 12: ...mplemented to prevent this from occurring If however a manual configuration is created or used by a user failure to ensure that only one Interlock Relay is ON will create a current overload possibly c...

Страница 13: ...Element Interlock and ensure it is ON 1 ENABLED Enable the PID Control and set it to strike temperature of 161 degrees F Start Timer X 5 After strike temp is reached turn PID Control OFF turn Pump 1...

Страница 14: ...prior to updating BruControl should be closed or disconnected from the UniFlex interface prior to updating the firmware UniFlex Interface Wiring Map Per the BruControl User Manual the application and...

Страница 15: ...ted I O Pin 2 input only UniFlex v2 BruControl Interface Wiring Map ESP32 Firmware v45 Connection TCP Network Connection Wiring Map Default Wiring Map Firmware Prefix BruControl 45_ ESP32 Firmware Pre...

Страница 16: ...d the output driver Power Connector for it The mating connectors for these two are included in the accessory kit The I O Connector is a 20 pin connector that provides connections to the 17 I O 12 high...

Страница 17: ...e analog output or the inputs The limits per high current driver output pin are 2 amps per driver output pin 5 amps per driver output pin bank and 12 amps total Note The mating I O and Power Connector...

Страница 18: ......

Страница 19: ...es power consumers such as relays or solenoids These drivers are electronic switches and require a power source to switch to the power consumers This source can either be the UniFlex internal power su...

Страница 20: ......

Страница 21: ...ropriate compression fittings should be used The temperature sensor is a 1 wire DS18B20 which operates on a bus type communication system This allows the UniFlex user to plug in multiple probes up to...

Страница 22: ...nting if desired The UniFlex may be mounted horizontally with the DIN rail clips facing down or vertically with the pigtail power cords hanging down Do not mount the unit in any other orientation The...

Страница 23: ...7 days of the delivery date of any shipping damage Customer is responsible for shipping damage outside of this time period Approval for return must be provided by BruControl LLC prior to any return Cu...

Страница 24: ...expense incurred due to manufacturing defects in material and workmanship or any other reason 4 Any performance of repairs after the warranty coverage period has expired or performance of repairs reg...

Отзывы: