REFRESH
INSTALLATION, OPERATION AND MAINTENANCE MANUAL
Assembly, Installation and Commissioning
All equipment installed below the Refresh Unit must either be:
o
Fully removable, or
o
Mounted or positioned in such a way as to allow regular access to the filter grease
drawer
o
Mounted or positioned in such a way as to allow regular access to the door on the Inside
face of the tower.
for reference.
This guide contains WARNINGS and Cautions regarding safety procedures that must be
followed.
2.3.2
Refresh Mini, Midi & Maxi Assembly Procedures
The following procedures cover only the Refresh Midi, Maxi and Ultima units as these units require
assembly. The refresh Mini is supplied a one-piece unit.
Step 1:
Prepare a clear & level area around the proposed installation area in accordance with
the drawings with approximately 1 metre clearance all-round the unit for access.
Note: The unit must be installed on a level surface.
Step 2:
Install the bottom unit in the proposed installation area.
Step 3:
Using the spirit level, make sure the bottom unit is level. Adjust the feet accordingly as
necessary and then recheck the level.
Step 4:
Using safe and suitable methods lift and then position the first half of the unit on top of
the base and lock into position.
Step 5:
Assemble the filters and cover panels to the unit as necessary.
Step 6:
To secure the unit to the building fabric (by others), at the top rear of the unit use the 2
looped end retaining wires.
2.3.2.1 Installing the Unit
Please note the following step guidelines must be taken into consideration during the installation of
BKV products.
WARNING:
COMPETENT PERSONNEL FAMILIAR WITH THE ASSESSMENT OF HAZARDS AND RISKS
ASSOCIATED WITH INDUSTRIAL ELECTRICAL AND VENTILATION EQUIPMENT SUCH AS
FANS AND AIR HANDLING UNITS SHOULD INSTALL THIS EQUIPMENT.
Step 1:
Check the unit is correctly assembled. Refer to
Section 2.2.4 Refresh Mini, Midi & Maxi
.
Step 2:
Where it is necessary to fix the unit against a wall:
Step a)
Using the battery powered equipment, Unistrut and fixings from the fixings
box, mount the unit against the wall.
Step b)
Using the spirit level, make sure the unit is still level.
Step c)
Using screws, plugs or anchors, fix the unit to the wall. Using a suitable tool,
tighten the fixings until the unit is fully secure.
Step 3:
Connect the main power lead to the incoming power supply.
Step 4:
Install the required filters, blanks and panels into correct openings and positions.
Step 5:
Complete the “On site final inspection” checklist.
Step 6:
The customer site contact or main contractor must inspect the completed installation
and sign the “Site installation form”. All comments, provisos or alternative instructions
given must be noted on this form. Leave a copy with signee for their records.