Turn off gas supply to water heater. Rotate the knob
of gas control/gas valve to the “OFF” position.
Remove the outer jacket door.
Remove right side of inner door per
Service Procedure RG-I, Steps 3a through 3c.
Disconnect thermocouple/thermopile, pilot tube,
and feedline from gas control/gas valve.
NOTE: Feedline nut for natural gas control uses
Step 1.
Step 2.
Step 3.
Step 4.
right hand threads, L.P. control uses left hand thread.
Disconnect piezo ignition wire from piezo igniter.
Remove burner assembly from the combustion chamber.
Remove the pilot/electrode assembly from the feedline.
Step 5.
Step 6.
Step 7.
Step 8. Inspect pilot for the following:
a) Primary air openings for blockage. Must be free from any
debris (dirt, lint, etc.).
b) Kinks or cracks in the pilot tube. If found,
the pilot must be replaced.
Step 9. Inspect pilot orifice (Honeywell ONLY):
a)Remove 7/16" nut from bottom of pilot assembly.
b) Remove pilot tube and pilot orifice.
c) Inspect pilot orifice for blockage, must be cleaned or
replaced. (Honeywell & White Rodgers Electronic pilot
orifice not replaceable, replace pilot assembly).
Step 10.
Step 11.
Step 12.
Step 13.
Install pilot/electrode assembly to feedline, secure with screw from Step 7.
Re-install burner assembly into combustion chamber, connect feedline,
pilot tube and thermocouple/thermopile to gas control/gas valve.
Install inner door per Service Procedure RG-I, “Installation of Inner
Door with Gasket.”
To resume operation, follow the instructions located on the lighting
instruction label or the lighting instructions located in the Installation
and Operation Manual.
PILOT/ELECTRODE ASSEMBLY INSPECTION, CLEANING, AND REPLACEMENT
SERVICE PROCEDURE RG-III
Pilot Assembly Inspection, Cleaning
and Replacement
Removal of thermopile from
Honeywell & White Rodgers
Electronic pilot assembly is
NOT recommended but can be
achieved by viewing the pilot
assembly from the top and
pressing the thermopile
towards the right while pulling
to remove.