Installation
3.5
Commissioning
Page 26
BOGE Operating instructions for C 10 L...C 20 L series screw compressors
–
Switch off compressor.
List up the test results in the commissioning certificate.
Opening the stop valves
Open ball valve on the compressor delivery.
Checking for leaks
Undertake the following to prevent leaks:
–
Check screw connection of the lines and retighten, if necessary.
Conduct trial run
–
Switch on the main switch.
–
Switch on the compressor using the ON key. The compressor starts.
–
When the factory-set switch-off pressure is reached, the compressor cuts
off automatically.
–
Check network pressure on control display. If necessary, reset operating
pressure.
–
The compressor is ready for operation.
Commissioning
following extended
stoppages
If an extended stoppage is scheduled, you should contact BOGE-Service
beforehand.
Following an extended stoppage of more than 2 months, fill a small amount of
oil in the suction controller prior to starting the compressor.
Caution: Risk of injury!
Press Emergency Stop button, open mains disconnection device and secure
against unintentional switch on by means of a padlock.
–
If necessary, have leakages repaired by skilled qualified pesonnel.
Caution: Risk of injury!
In case of leakages in the oil circuit there is a certain danger to slip and fall
because of oil spills!
Have all connections of the oil circuit checked for leakages by authorized
qualified personnel!
During the inspection slip-resistant safety shoes and protective clothing are
obligatory!
Attention!
Only fill the suction controller with the grade of oil used to operate the com-
pressor.
Never mix different oil grades and brands.