STL3500
13
VI) INSTALLATION
The lift must be installed taking into account the dimensions of the vehicles to be lifted, and the specified distances from
the walls, columns, other machinery, etc. The room must be at least 4500mm in height. The minimum distance from the
walls must be 2000mm (see diagram page13)
FLOOR
The lift must be installed on a flat, horizontal and sufficiently sturdy floor, with a minimum strength of 250Kg/cm².
(Concrete C30 / 37 according to NF EN206 / CN)
(Concrete C35 / 45 according to NF EN206 / CN when installation is made inside a KOREK Frame)
WARNING
Only skilled and authorized technicians must install the lift.
No unauthorised person should be present during installation.
WARNING
Unpack the goods and check for possible damage before installing the lift.
WARNING
Before working inside the control unit either for connecting the electric supply or for the repair of faults, make
sure the main power supply has been disconnected to avoid any risk of electrocution.
INSTALLATION PROCEDURE
First connect the electric and hydraulic systems before connecting the pneumatic system of the lift.
1. Check for availability of power supply
First of all, ensure that the power supply is equipped by a magneto-thermic switch (380V -16A with protection fuses) with
suitable protection devices conforming to local safety regulations and that the maximum distance of the electrical
connections and the hydraulic connections from the control unit is 3 metres.
Open the front panel of the control unit in order to make the connections.
2. Positioning of the lift
Ensure that the lift is positioned exactly in the centre of the pit frame.
Position the lift using a forklift, crane or other suitable means. Eliminate the possible slight floor level differences (max
7mm) using metallic wedges (Not supplied by BLACKHAWK®).
This is necessary in order to not affect the warranty.
For installations inside a KOREK frame, please refer to the layout supplied by BLACKHAWK®.
The lift must always be level.