Section 2: Installation
Installation
2.7
Commissioning
!
WARNING
Check that values of electrical supply to the control group (if foreseen) are compatible
with those on the plate on the junction box (Figure 11). Installation, commissioning and
maintenance and repair works should be made by qualified staff.
Upon actuator commissioning, please carry out the following checks:
•
Check that paint is not damaged during transport. If necessary, repair the
damages to paint coat.
•
Before start up and after every 6 months, check accumulator pre-charging
pressure (please check the value in technical data sheet supplied).
•
Check that the values of hydraulic supply available in the system are compatible
with those reported on the identification plate of the actuator (Figure 1) and on
the documentation supplied.
•
Check that the feed voltage values of the electric components (solenoid valve
coils, microswitches, pressure switches, etc.) are compatible with those reported
on the identification plate of the actuator (Figure 1).
•
Check that the setting of the components of the actuator control unit
(pressure regulator, pressure switches, flow control valves, etc.), meet the
plant requirements.
•
Carry out all kinds of operations and check their proper execution (Section 3.3).
•
Check the absence of leakages in the cylinder and in hydraulic connections. If
necessary, tighten the nuts of the pipe-fittings.
•
Check proper operation of all the due signalling (valve position, supply
pressure, etc.).
•
Make a complete functional test in order to verify all the operations are executed
according to operating schematic diagram supplied.