42-3/8" Long 2x3
Step 13 Install Rear Gable Trim
1
Install (4) four small OSB fillers, packed with
the hardware, over the 2x4 soffit blocks. Fillers
will be flush with the gable OSB. Use 6d
common nails.
OSB Filler
4.
Gather (2) two 82-1/2" long 1x4 trim boards. Butt
each board against the keystone and flush with the
top of the gable frame. Use 6d galv. nails.
Side Wall
Back Wall
The front gable trim will be installed
in a later step.
Keystone
82-1/2" Long 1x4 Trim
Rear Gable
2.
Install (4) four 42-3/8" long 2x3 boards
on the rear gable flush with the top of
the gable frame. Use 10d sinkers
3.
Install a 8-1/2" long trim board,
called a keystone, at the top of the
gable flush with the top of the
gable frame. Use 6d galv. nails.