Directions for Wiring a 6-Volt Series/Parallel, 4 Battery NITE Phoenix
Step 1: Make and install the two short battery cables. These cables
connect the positive (+) of one battery to the negative (-) of the other to
create a set or bank. We refer to this as a series connection.
See
drawing below.
DO
N’T connect any other cables or wires to these
terminals
.
Step 2: For the positive to positive parallel connections, measure and cut
a piece of red cable to the proper length. Attach a ring terminal to each
end using a professional grade crimper. Place heat shrink around each
terminal and heat. Then loom it. Use this cable to connect the positive (+)
of one bank of batteries to the positive (+) of the other bank of batteries.
Step 3: Repeat Procedure for the negative to negative connection using
black cable. Then loom it. Use this black cable to connect the negative (-)
of one bank of batteries to the negative (-) of the other bank of batteries.
Do NOT use truck frame as a ground
Battery Set
Battery Set
Connect positives
here: AC unit, Heater
and separator
Connect negatives
here: AC Unit,
heater, and Truck
Battery negative
BMS
=Battery Management System
Electrical Installation
Electrical Installation
=12V
5a
Содержание NITE Phoenix T2000
Страница 8: ...8 1 6 Before You Start EPA ...
Страница 9: ...9 1 7 Cardboard Template Layout Unit Exploded View ...
Страница 24: ...24 Section 2 Electrical Installation ...
Страница 42: ...42 2 18 Electrical Installation ...
Страница 46: ...46 Section 3 ESPAR Fuel Operated Heater Installation ...
Страница 60: ...60 New Phoenix wiring for units built from 6 26 2017 to current 4 2 Wiring Diagrams ...
Страница 61: ...61 Use for units manufactured from 2 08 2012 to 6 26 2017 4 3 Wiring Diagrams ...
Страница 62: ...62 Use for units manufactured from 2 08 2012 to 6 26 2017 4 4 Wiring Diagrams ...
Страница 63: ...63 Use for units manufactured prior to 2 08 2012 4 5 Wiring Diagrams ...
Страница 64: ...64 Use for units manufactured prior to 2 08 2012 4 6 Wiring Diagrams ...
Страница 65: ...65 Section 5 Operating Instructions ...
Страница 69: ...69 Section 6 Battery Management System BMS Installation ...
Страница 70: ...70 6 1 Bergstrom NITE System BMS 100 Installation Battery Management ...
Страница 71: ...71 6 2 Battery Management ...
Страница 72: ...72 6 3 Battery Management ...