Initial Startup Procedures
Install Spray Nozzles & Verify Proper Function of Top Assembly and Airis®
5) In each Top Manifold Assembly install four (4) of the supplied Spray Nozzles into the Check
Bodies, refer to the image below.
Note:
Lubricate the Nozzle threads with a Liquid-Teflon™ for easier installation and maintenance.
6) Rotate each Spray Nozzle so it is installed at a 5° angle to the centerline of the Manifold. Be sure
to rotate all of the nozzles in the same direction, see the image below.
Apply Liquid Teflon™ to the
Nozzle Threads at Installation
Check Bodies
Four (4) per Top Manifold
Spray Nozzle
Four (4) Nozzles per Manifold
Eight (8) Nozzles in Top Assembly
Top Manifold (2)
5°
Centerline of
Manifold