Microseparator™ Coolant Systems Transport, Installation, & Initial Startup
M000005_A - V Twin Ultra Transport & Installation 5.2-EN TM
57/78
18.13.1
Connecting Electrical Power
Connect mains power to main panel through pigtail provided, listed as
Figure 38 - Pump Station Connections
on page 53
electrical drawings supplied with the Machine for further detail. Make the
following checks:
Test the local rotary field. Your machine is designed for a right rotating
field. It may be necessary to observe impeller rotation using a mirror and
flashlight. Set per pump arrow. Test all screw terminals as well as
contactors, relays, and fuses for proper fit.
18.13.2
Pump Station Operation
See the MICROSEPARATOR™ OPERATION MANUAL for detailed
instructions concerning the Pump Station operation. The documentation
is supplied inside the electrical control panel along with the panel wiring
diagrams.