background image

9.0 Plume Displacement

28

© Baxi Heating UK Ltd 2012

1

0

2

4

6

8

10

12

14

70Ø Exhaust (metr

es)

Concentric 70/110 Flue (metres)

0

16

18

2

3

4

20

12,

 15,

 18 & 24

30 

22

24

26

28

30

1

0

2

4

6

8

10

12

14

70Ø Exhaust (metr

es)

Concentric 70/110 Flue (metres)

0

16

18

2

3

4

20

12,

 15,

 18 & 24

30 

22

24

26

28

30

1

0

2

4

6

8

10

12

14

70Ø Exhaust (metr

es)

Concentric 70/110 Flue (metres)

0

16

18

2

3

4

20

12,

 15,

 18 & 24

30 

22

24

26

28

30

Flue Length - Worked Example
Baxi Solo 30 HE 

A

In Fig. D opposite an additional 93° elbow and pair of 45°
elbows have been included in the 70Ø exhaust.
Also 3 straight extension pieces have been used.

To calculate total length:-
Length of 70Ø supplied in kit = 

1 metre

3 x 1 metre Extensions =

3 metres

1 x 93° Elbow =

1 metre

2 x 45° Elbow =

1 metre (0.5 metres each)

Total 70Ø =

6 metres

After consulting the table in Example 3 it can be determined
that the concentric flue could be up to approximately 3.25
metres long.

Concentric Flue

Support
Bracket

45° Elbow

93° Elbow

1 metre Extension

1 metre supplied in kit

Additional Accessories

A - 93° Elbow

5121373

B - 45° Elbow (Pair)

5121374

C - 1 metre 70Ø Extension 5121372

9.2

Determining Permissible Lengths - P.D.K.

In the graph the solid line diagonal represents the
relationship between the concentric flue assembly (and any
extensions) and the 70Ø exhaust (and any extensions or
additional bends).

Example 1 - Not Permissible

If, for instance, a concentric length of 3.25 metres was
required and the 70Ø exhaust needed to be 10 metres the
graph shows that this combination would NOT be
permissible as the intersection point would be above the
solid diagonal line.

Example 2 - Flue Lengths OK

Where both lengths have been determined they can be
applied to the graph to check that the installation is
permissible. For example, if it was known that 2 metres of
concentric flue and 4 metres of 70Ø exhaust were required,
the values could be applied to the graph as shown in
Example 2.. As the point of intersection of the dotted lines is
below the solid diagonal line, the combination of lengths is
shown to be acceptable.

Example 3 - Flue Lengths OK

In the example shown, assume that the concentric part of
the flue needs to be 2 metres long. Find the position of ‘2’ on
the horizontal axis of the graph and then project upwards to
the solid diagonal line. This is represented by the vertical
thick dotted line. Where this dotted line intersects with the
solid diagonal line on the graph, project across to the vertical
axis. As can be seen this corresponds with 14 metres.
Therefore, the total equivalent length of the 70Ø exhaust
can be up to 14 metres. Any elbow equivalencies must be
accounted for i.e. 93° elbows are equal to 1 metre, each 45°
elbow to 0.5 metres. 

Example 1
Flue Lengths - Not Permissible

Example 2
Flue Lengths - OK

Example 3
Flue Lengths - OK

Concentric 70/110 Flue
(MUST be installed
horizontally)

70Ø Exhaust

X

Y

Fig. D

Содержание Solo 12 HE

Страница 1: ...A Range Wall Mounted Powered Flue Condensing Boilers Gas Fired Central Heating Units Installation Servicing Instructions These instructions include the Benchmark Commissioning Checklist and should be left with the user for safe keeping ...

Страница 2: ...only relates to dwellings Therefore the checklist only applies if the appliance is being installed in a dwelling or some related structure The flowchart opposite gives guidance for installers on the process necessary to ensure compliance with Building Regulations Baxi Heating UK Ltd 2012 All rights reserved No part of this publication may be reproduced or transmitted in any form or by any means or...

Страница 3: ...elevant LABC You must ensure that the certificate number issued by the Gas Safe Register is written onto the Benchmark Checklist Scheme Members only Call Gas Safe Register on 0800 408 5577 or log onto www gassaferegister co uk within 10 days If you notify via the Gas Safe Register the register will issue the Building Regulations certificate on members behalf Complete the Benchmark Checklist Instal...

Страница 4: ...Practice apply Standard Scope I S 813 Domestic Gas Installations The following BS standards give valuable additional information BS 5546 Installation of hot water supplies for domestic purposes BS EN 12828 Heating systems in buildings BS EN 12831 Heating systems in buildings calculations of load BS EN 14336 Installation commissioning of water based heating systems BS 7074 Expansion vessels and anc...

Страница 5: ...oute is clear and unobstructed If possible avoid steps wet or slippery surfaces unlit areas etc and take special care on ladders into lofts Technique When handling or lifting always use safe techniques keep your back straight bend your knees Don t twist move your feet avoid bending forwards and sideways and keep the load as close to your body as possible Where possible transport the boiler using a...

Страница 6: ...ue Options 22 9 0 Plume Displacement 27 10 0 Installation 31 11 0 Electrical 37 12 0 Commissioning the Boiler 39 13 0 Fitting the Outer Case 41 14 0 Servicing the Boiler 42 15 0 Changing Components 45 16 0 Short Parts List 51 17 0 Fault Finding 52 Benchmark Checklist 58 Section Page Contents Contents of Pack The pack contains Boiler Wall Plate Template Quick Fit Guide Literature Pack Fittings Pack...

Страница 7: ... rear of the lower door panel Fig 1 6 The boiler data badge is positioned on the air box door Fig 2 7 The boiler is intended to be installed in residential commercial light industrial E M C environments on a governed meter supply only 8 The boiler must be installed with one of the purpose designed flues such as the standard horizontal flue kit part no 236921 1 2 Important Information Man made mine...

Страница 8: ... Protection Thermostat 7 Fan Assembly 8 Condensate Trap 9 PCB Housing Assembly 10 Gas Tap 11 Gas Air Ratio Valve 12 Flow Pipe Connection 13 Return Pipe Connection 14 Flow Temperature Safety Thermostat Black 15 Flow Temperature Thermistor Red 16 Flow Switch dry fire protection 1 2 3 4 5 6 7 9 8 10 11 15 14 12 13 16 Fig 4 Fig 3 Fig 5 Fig 6 ...

Страница 9: ...and thereby the gas rate to achieve optimum operation If the flow temperature is greater than the set point or the TRVs all shut down then fan post purge occurs 6 Fan Post Purge The pump and fan are on while the spark generator and gas valve are off After 5 seconds if the TRVs are not shut down then pump overrun occurs After 5 seconds if the TRVs are shut down then anti cycle occurs 7 Pump Overrun...

Страница 10: ... Clearances For unventilated compartments see Section 7 2 Both Sides 5mm Min Above Casing 200mm Min Below Casing 50mm Min Front For Servicing 500mm Min Front In Operation 5mm Min Appliance Type C13 C33 C53 Nox Class 5 Heat Output P Condensing 40 C Mean Water Temp Max Min 12 model kW 12 81 15 model kW 16 49 10 1 18 model kW 19 27 24 model kW 23 8 10 1 30 model kW 32 61 10 1 Water Content litres 2 6...

Страница 11: ...ove the top of the flue elbow should be 27 5mm to incorporate the 1 5 fall in the flue from the terminal to the elbow The 1 5 fall provided by the elbow is to allow condensate to run back to the boiler for disposal through the condensate discharge pipe Flue length Y up to 1m 1m 2m 2m 3m Clearance X 27 5mm 55mm 82 5mm 360 Orientation Tube Ø 110mm D C B A E F Y At least 1 5 X At least 1 5 Fig 7 Fig ...

Страница 12: ...udge accumulates within the system risking damage to pump and valves boiler noise and circulation problems When fitting new systems flux will be evident within the system which can lead to damage of system components All systems must be thoroughly drained and flushed out using for example Sentinel X300 or X400 or Fernox F3 They should be used following the flushing agent manufacturer s instruction...

Страница 13: ... a 20 C drop across the boiler b The pump must be fitted on the flow c The pump must be fitted in accordance with the pump manufacturer s instructions d The open vent pipe must be taken up from a tee in a horizontal section of the flow pipe An alternative Low Head Installation Fig 12 2 For heads below 400mm then a combined vent and feed pipe may be connected This must be a minimum of 22mm diameter...

Страница 14: ...L N CH on HW on HW off L N E L N P F E b g y w o gr 1 C 2 g y S Plan Valve Cylinder Stat Room Stat Boiler Pump Timer 230V 50Hz L N E L N CH on HW on L N E L N P F E Motor S Plan Valve Motor o o gr b g y b gr br br Y Plan Diverter Valve Cylinder Stat Boiler Pump Timer 230V 50Hz L N E L N CH on HW on HW off L N E L N P F E b g y o gr 1 C 2 w g y S Plan Valve Cylinder Stat Boiler Pump Timer 230V 50Hz...

Страница 15: ...ply pipe provided a Listed double check valve or some other no less effective backflow prevention device is permanently connected at the inlet to the circuit and the temporary connection is removed after use The filling method adopted must be in accordance with all relevant water supply regulations and use approved equipment Your attention is drawn to for GB Guidance G24 2 and recommendation R24 2...

Страница 16: ...de to the relevant requirements In GB this is the current I E E Wiring Regulations and Building Regulations In IE reference should be made to the current edition of I S 813 Domestic Gas Installations and the current ETCI rules 4 If the boiler is to be fitted into a building of timber frame construction then reference must be made to the current edition of Institute of Gas Engineers Publication IGE...

Страница 17: ...ce is of adequate size to ensure correct operation Do not use pipes of a smaller diameter than the boiler gas connection 7 5 Electrical Supply 1 External wiring must be correctly earthed polarised and in accordance with relevant regulations rules In GB this is the current I E E Wiring Regulations In IE reference should be made to the current edition of ETCI rules 2 The mains supply is 230V 50Hz fu...

Страница 18: ...diameter and must be supported using suitably spaced clips of the correct design to prevent sagging 6 It is advisable that the full length of condensate pipe is run internally and preferably be less than 3 metres 7 Internal runs greater than 3 metres or runs in cold areas should use 32mm waste pipe 8 External runs MUST be a MINIMUM of 32mm and fully insulated with material suitable for external us...

Страница 19: ... emptied then back pressure may force water out of the boiler trap and cause appliance lockout Boiler 2 5 Minimum fall iii Termination to a drain or gully Boiler 500mm min 2 5 Minimum fall iv Termination to a purpose made soakaway Holes in the soak away must face away from the building 50mm per metre of pipe run 50mm per metre of pipe run Further specific requirements for soakaway design are refer...

Страница 20: ...ce Heating Element is NOT a substitute for correct installation of the condensate drain ALL requirements in this section must still be adhered to Boiler vi pumped into an external soil vent pipe 2 5 Minimum fall 50mm per metre of pipe run Condensate Pump Unheated Location e g Garage Basement or similar heated Boiler 2 5 Minimum fall 50mm per metre of pipe run Pipe must terminate above water level ...

Страница 21: ...we recommend the use of the plume displacement kit The terminal position must ensure the safe and nuisance free dispersal of combustion products Fig 17 Fig 16a 300 min Terminal Assembly TopView Rear Flue Property Boundary Line NOTE The distance from a fanned draught appliance terminal installed parallel to a boundary may not be less than 300mm in accordance with the diagram below Opening Window or...

Страница 22: ...3 bend 1 0 m NOTE Flue length is measured from point X to Y as shown IMPORTANT All flue systems must be securely supported at least once every metre Suitable pipe supports are available as accessories X Y X Y Plume Displacement 70 110 dia Kit 1M Extensions 45 93 bends are also available see Section 9 0 NOTE Horizontal flue pipes should always be installed with a 1 5 fall from the terminal to allow...

Страница 23: ...tal equivalent length for this example is 17 2 34 4 51 6 metres 1m extension 135 bend 91 5 bend 1m 1 3m 4 8m 5 2 2 5 0m 2 6m 9 6m AIR DUCT No of fittings pipes Sub total Equivalent Length Value Equivalent Length Air Duct 17 2m 1m extension 135 bend 91 5 bend 2m 2 6m 9 6m 5 2 2 10 0m 5 2m 19 2m FLUE DUCT No of fittings pipes Sub total Equivalent Length Value Equivalent Length Flue Duct 34 4m Y X C ...

Страница 24: ...10mm 243014BAX T Vertical Flue Boiler Adaptor 5106888 S Flue Terminal Deflector 248167 FLUE GROUP P Twin Flue System 80mm diameter E Flue Extension 1000mm 246137 500mm 246136 250mm 246135 F Flue Bend pair 90 5121560 G Flue Bend 2 pair 135 5121561 J Vertical Flue Boiler Adaptor Kit 242757 W Pipe Support pair 80mm 5111081 FLUE GROUP B P Vertical Flue Kits K Vertical Flue Terminal 242802 L Pitched Ro...

Страница 25: ...te 2 Fix the vertical adaptor and gasket to the top panel with the previously removed screws 8 5 For Twin Flue Systems 1 Undo the screws securing the blanking plate to the boiler top panel Discard the plate 2 Fix both the air and flue adaptors with their gaskets onto the boiler top panel Secure with screws For Vertical Flues For Twin Flues Air Duct Adaptor Flue Duct Adaptor Gasket Gasket ...

Страница 26: ...and secure to the roof structure with the clamp supplied IMPORTANT If the boiler is not fitted immediately after the flue system temporary precautions must be taken to prevent rain entry into the room of installation Any precautionary measures must be removed prior to commissioning the boiler 8 7 Flue Dimensions The standard horizontal flue kit allows for flue lengths between 270mm 105 8 and 800mm...

Страница 27: ...h the 70 110 concentric and 70Ø exhaust 5 Standard concentric flue extension kits may be added between the boiler elbow and the terminal assembly 6 The minimum length of the concentric flue is 100mm when measured from the edge of the boiler flue elbow There is a further 45mm engagement into the elbow IMPORTANT The maximum equivalent length of concentric flue is 4 metres Additional elbows may be fi...

Страница 28: ...tional bends Example 1 Not Permissible If for instance a concentric length of 3 25 metres was required and the 70Ø exhaust needed to be 10 metres the graph shows that this combination would NOT be permissible as the intersection point would be above the solid diagonal line Example 2 Flue Lengths OK Where both lengths have been determined they can be applied to the graph to check that the installat...

Страница 29: ...support the concentric assembly and any extensions and make good inside and outside Secure the flue trim to the wall 9 The 70Ø exhaust can now be fitted to the spigot at the terminal end 10 If it is necessary to shorten the 70Ø exhaust or any of the extensions the excess material must be cut from the plain end of the pipe 11 Determine the position of the 70Ø exhaust and mark on the wall a suitable...

Страница 30: ...t in an enclosed box but the air inlet and plume outlet MUST remain in free air 17 It is also possible to separate the plume outlet from the 93 elbow to allow the flue to be installed as shown in Fig H 18 When the plume outlet is positioned under a balcony or other projection Figs I J it must protrude at least 200mm it is not necessary to extend it further than this 200mm Min Fig H Fig I Fig J ...

Страница 31: ...ue minimum diameter 127mm see table Fig 20 for wall thicknesses and flue diameters 6 Drill and plug the wall as previously marked Secure the wall plate using the centre hole Fig 22 7 Ensuring the wall plate is level both horizontally and vertically drill and plug at least 4 securing positions at the top and bottom through the wall plate Utilising the slots available ensure the wall plate is square...

Страница 32: ...Ltd 2012 10 2 Preparing The Boiler Figs 22a 23 1 Remove the outer carton and packaging 2 Lift the outercase upwards and remove 3 Remove the internal packaging Lower Door Panel Outercase Fig 23 Break Off Upper Lower Pipe Run Options Fig 22a ...

Страница 33: ... and RETURN connections 10 4 Making the Water Connections Fig 25 1 The boiler has two side water connections which are labelled FLOW and RETURN The front connection is the flow pipe and the rear threaded connection is the return 2 It is essential that the flow and return pipes are connected to the boiler correctly The flow connection incorporates the boiler thermostats and a flow switch 3 The boil...

Страница 34: ...ness 181 3 Take the flue and mark off X from the terminal end as indicated in the diagram Fig 27 Check your dimensions The flue tubes are fixed together Cut through both tubes whilst resting the flue on the semi circular packing pieces Deburr both tube ends 4 For side exit measure the distance from the edge of the wall plate to the inner face of the wall Fig 26 and to this dimension add the wall t...

Страница 35: ...on on top of the boiler Secure with the four screws supplied in the kit 11 Make good between the wall and air duct outside the building ensuring the 1 5 drop between the terminal and elbow 12 The flue trim should be fitted once the installation is complete and the flue secure Fig 30 Apply a suitable mastic to the inside of the trim and press against the wall finish making sure the brickwork is dus...

Страница 36: ...e the Red jumper labelled CN12 from the bottom left hand side of the PCB c Hinge back up the PCB housing and secure with screw 4 Route the incoming electrical cable s through the grommet in the support bracket This will prevent damage to the cable 5 Lay the cable through the cable clamp to gauge the length of cable required when it is connected to the 4 way terminal block 6 Connect the S L N and w...

Страница 37: ...een g y Green Yellow op Opaque y Yellow Gas Valve g op Spark Electrode g y bk bk bk bk r w w Flame Detection Electrode Condensate Trap Flow Overheat Thermostat Fan Overheat Thermostat g y r b r r Flow Thermistor 325Vdc DC Fan CH Flow Switch gy gy w g br PCB Earths not shown to aid clarity of diagram g y b y L N Optional Pump Feed br g y br b op op ...

Страница 38: ...p Opaque y Yellow 11 2 Illustrated Wiring Diagram GasValve Fan CondensateTrap CH Flow Switch Flow Thermistor Spark Electrode Flame Detection Electrode Main PCB N L r r gy gy r b br g w Flow Overheat Thermostat Fan Overheat Thermostat bk bk bk r bk w w op g y g y Layout of PCB Pins Optional Pump Feed g y br y g y b br b y b br br ...

Страница 39: ...s 7 Remove the top RH securing screw and hinge down the PCB housing to gain access to the gas service cock see Fig 32 Turn the gas service cock anticlockwise to the ON position and check for gas tightness up to the gas valve Fig 34 NOTE The 12 15 18 24 are self regulating dependent upon the system load The 30 HE A will modulate between inputs of 33 76kW and 10 3kW The 30 HE A input is factory set ...

Страница 40: ... lights turned OFF the gas rate can be measured It should be as shown in Section 4 0 Technical Data 5 Carefully read and complete all sections of the Benchmark Commissioning Checklist at the rear of this publication that are relevant to the boiler and installation These details will be required in the event of any warranty work The publication must be handed to the user for safe keeping and each s...

Страница 41: ...mplete a Declaration of Conformity to indicate compliance to I S 813 An example of this is given in I S 813 Domestic Gas Installations This is in addition to the Benchmark Commissioning Checklist 6 Instruct the user in the operation of the boiler controls Hand over the User s Operating Installation and Servicing Instructions giving advice on the necessity of regular servicing 7 Demonstrate to the ...

Страница 42: ...n for Installation Maintenance of Gas Fired Boilers not exceeding 70kW advises that The person carrying out a combustion measurement should have been assessed as competent in the use of a flue gas analyser and the interpretation of the results The flue gas analyser used should be one meeting the requirements of BS7927 or BS EN50379 3 and be calibrated in accordance with the analyser manufacturers ...

Страница 43: ...cess 7 Release the four 1 4 turn screws securing the air box door panel and remove the door Fig 39 8 Disconnect the leads from the centre and right hand terminals earth and flame sensing probe Fig 40 Reconnect in reverse order 9 Undo the four screws securing the combustion box door and remove the door Fig 41 10 Visually check for debris damage and clean or replace if necessary the following a Burn...

Страница 44: ...mbustion box base and withdraw the base j Lower the central insulation panel and check condition Fig 44 Replace the lower insulation pad if necessary k Ensure the heat exchanger fins are clear of any obstruction l Check condition of all seals Important Pay particular attention to the condition of the combustion box door seals m Reassemble in reverse order and check for leaks 11 Check CO CO2 ratio ...

Страница 45: ... before access 3 Isolate the water circuit and drain the system as necessary A drain point is located on the heat exchanger manifold at the right hand side of the boiler Fig 45 to enable the heat exchanger to be drained 4 Place a tube on the drain point to drain water away from electrics Turn anticlockwise to open Fig 45 NOTE When reassembling always fit new O rings ensuring their correct location...

Страница 46: ...ip Flow Pipe Fig 47 Support Bracket 15 4 PCB Figs 48 49 WARNING The PCB Control and Fan Assembly are 325 Vdc Isolate at supply before access 1 Pull the control knob off the spindle and remove the plastic button cover Refit them onto the new PCB Fig 48 2 Remove the top right hand securing screw and hinge down the PCB housing and disconnect the electrical connections noting their positions NOTE Chec...

Страница 47: ... WARNING The PCB Control and Fan Assembly are 325 Vdc Isolate at supply before access 1 Loosen the screw holding the injector pipe into the venturi 2 Remove the electrical connections to the fan and protection sensor on the fan 3 Remove the wing nuts securing the fan to the base of the combustion box 4 Lower the fan and remove 5 If changing the fan remove the screws securing the venturi and fan pr...

Страница 48: ...the air box holding the gas valve 7 Remove the gas valve from the airbox side 8 Remove the aluminium spacer and its gasket from the gas valve 9 Fit the aluminium spacer and its gasket to the new valve 10 Fit the new gas valve and reassemble in reverse order NOTE Check for gas tightness after replacing gas valve 11 Check the CO2 level If the level is greater than that quoted telephone the Technical...

Страница 49: ...it the new burner and reassemble in reverse order 15 11 Heat Exchanger 1 Drain the boiler see section 15 1 paragraph 2 3 2 Remove all components in the base of the airbox 3 Undo the screws on the support bracket Remove the screws securing the flow switch and return connections and remove the connections Fig 57 4 Remove the screws securing the heat exchanger manifold and remove the manifold Fig 58 ...

Страница 50: ...anger and remove the lower insulation pad 6 Fit the new insulation pad and reassemble in reverse order 15 13 Heat Exchanger Upper Insulation Pad Fig 60 1 Remove all components in the base of the airbox 2 Remove the burner see section 15 10 3 Remove the heat exchanger see section 15 11 4 Remove the four bolts securing the combustion box base 5 Remove the combustion box base 6 Pull the central insul...

Страница 51: ...erature Thermistor Red 240670 B E06 059 Flow Switch 242459 C E06 060 Safety Thermostat Black 242235 D PCB 5129147 E Fan 5109925 F Gas Valve 241900 G E06 085 Viewing Window 242484 H Condensate Trap 5111714 I Electrodes Kit 5132097 J Burner Assy 5107430 K E06 097 Heat Exchanger Assy 242497 L Control Knob 5109996 A B C E F G H I J K D L ...

Страница 52: ...ts replace LV wiring harness PCB Fault Replace PCB PCB Fault Replace PCB PCB Fault Replace PCB YES YES YES YES YES YES YES YES YES YES YES YES Go to Electrical Supply section of the fault finding instructions ON Go to Dry Fire section of the fault finding instructions Go to Overheat Lockout section of the fault finding instructions NOTE The fan is supplied with 325 Vdc Fan Fault Finding should onl...

Страница 53: ...Systems Controls and System Wiring 240V at B Check wiring from terminal block to PCB Check for shorts on pump fan gas valve Replace if shorted replace fuse YES NO Replace PCB YES YES NO NO ELECTRICAL SUPPLY 240V at A PCB fuse OK B Fuse A N L Lights Off Off Off ON Optional Pump Live ...

Страница 54: ...off on After 5 sec is there 240V at E Pump or Pump Wiring fault Is there a blockage in the system NO YES YES E Optional Pump Live N L F N L Turn mains off unplug 7 way connector to PCB Is there continuity between F and G Wiring from terminal block to PCB faulty NO YES Replace PCB Wires from inline connector to PCB faulty Remove flow switch from boiler Is there a physical blockage to the paddle wit...

Страница 55: ...e as necessary YES YES NO NO YES Remove Gas Valve check inlet filter for blockage Otherwise incorrect gas supply to boiler Is there at least 18mbar dynamic at gas valve inlet Lead from PCB to Gas Valve faulty Is spark gap between 3 and 4mm Replace spark or flame detection probe and gaskets Is wiring from PCB to spark probe flame detection probe OK NO YES NO NO YES YES NO NO I Remove the larger or ...

Страница 56: ...bustion chamber door seal trim seal NO YES NO YES Reconnect stat Disconnect fan stat When fan temp 60 C is there continuity across stat Reconnect stat Disconnect the larger of the 6 way PCB connectors Is there continuity across M Disconnect thermistor red sensor on flow pipe Is resistance between 0 5kè 20kè Is combustion chamber door seal damaged or not in place Replace PCB YES Replace thermistor ...

Страница 57: ...Wire Entry end S W Fan Connection PCB Connection Fan Connection PCB Connection NOTE The fan is supplied with 325 Vdc Fan Fault Finding should only be carried out after the boiler has been electrically isolated Lights Flash Flash On ON THERMISTOR Replace thermistor Wiring from PCB to thermistor faulty YES NO NO YES Replace PCB Unplug thermistor Is thermistor resistance between 0 5kè 20kè Plug in th...

Страница 58: ...em cleaner was used Gas Rate Burner Operating Pressure if applicable Central Heating Flow Temperature Central Heating Return Temperature Gas Rate Burner Operating Pressure at maximum rate Cold Water Inlet Temperature Hot Water has been checked at all outlets If required by the manufacturer record the following The heating and hot water system complies with the appropriate Building Regulations The ...

Страница 59: ...r Name Company Name Telephone No Gas Safe Register No Comments Signature Date Engineer Name Company Name Telephone No Gas Safe Register No Comments Signature Date Engineer Name Company Name Telephone No Gas Safe Register No Comments Signature Date Engineer Name Company Name Telephone No Operative ID No Comments Signature Date Engineer Name Company Name Telephone No Gas Safe Register No Comments Si...

Страница 60: ...l Enquiries 0844 871 1555 Website www baxi co uk e oe All descriptions and illustrations provided in this leaflet have been carefully prepared but we reserve the right to make changes and improvements in our products which may affect the accuracy of the information contained in this leaflet All goods are sold subject to our standard Conditions of Sale which are available on request ...

Отзывы: