Operation manual for
BAUER RAINSTAR
Series T32, T42
20
6.3
OPERATING MODE I: PE-PIPE PULL-OFF
6.3.1 MACHINE SET-UP
4
Adjust the parked machine with the jack in as level a position as possible.
5
For lateral PE-pipe pull-off, remove the lock pin, turn the reel into the irrigation lane, and secure it again
with the lock pin.
For straight PE-pipe retraction the pipe reel must point exactly into the direction of the irrigation lane.
6
Pull out the bolts of the machine-support transport guards.
When the bolts are removed the machine supports slide to the ground automatically.
7
Drive the supports into the ground by means of the detachable hand wheel.
8
Secure the bolts with pins.
Make sure that the RAINSTAR stands firmly and cannot alter is position during the
run.
WARNING!
If the supports do not dig into the ground sufficiently on hard soil in spite of the sharp
shields, holes must be provided in the soil into which the supports are lowered, in
order to guarantee sufficient machine stability.
WARNING!
WARNING