IMPORTANT! -

 The overload will then 

automatically  reset  and  start  the 
pump  up  after  the  motor  cools  to  a 

safe  temperature.  In  the  event  of  an 

overload, the source of this condition 

should be determined and corrected 

immediately. 

If  current  through  the  temperature 

sensor  exceeds  the  values  listed,  an 

intermediate  control  circuit  relay 
must  be  used  to  reduce  the  current 
or the sensor will not work properly.

TEMPERATURE SENSOR ELECTRICAL 

RATINGS

Volts

Continuous

Amperes

Inrush

Amperes

110-120

3.00

30.0

220-240

1.50

15.0

440-480

0.75

7.5

600

0.60

6.0

Wire Size:

If  longer  power  cable  is  required 
consult  a  qualified  electrician  for 
proper wire size.

04

Installation & Service

DO  NOT  ALLOW  THE 

PUMP  TO  CYCLE  OR  RUN  IF  AN 
OVERLOAD CONDITION OCCURS.

WARNING

Pre-Operation

Check  Voltage  and  Phase  - 

Compare  the  voltage  and  phase 
information  stamped  on  the 
pump name plate.

Kickback  should  always  be  in  a 

counter-clockwise 

direction 

as 

viewed  from  motor  end  or  opposite 

to impeller rotation. Impeller rotation 
is  counter-clockwise  as  viewed  from 
bottom of pump.

Name  Plate  - 

Record  the 

information from the pump name 

plate  to  drawing  in  front  of 

manual for future reference.

a) Inspect motor chamber for oil level 

and contamination.

b)  Inspect  impeller  and  body  for 

excessive build-up or clogging.

c) Inspect motor, bearings and shaft 

seal for wear or leakage.

No  lubrication  or  maintenance  is 

required.  Perform  the  following 
checks when pump is removed from 

operation 

or 

when 

pump 

performance deteriorates:

Maintenance

NOTE:  Item  numbers  in  (  )  refer  to 

Figure 5.

Servicing

After leak is repaired, dispose of old 
oil properly, and refill with new oil.

Insulation  Test  - 

An  insulation 

(megger) 

test 

should 

be 

performed  on  the  motor.  Before 
the pump is put into service. The 
resistance values (ohms) as well as 
the  voltage  (volts)  and  current 

(amps) should be recorded.

Pump-Down Test - 

Be sure pump 

has been properly wired, lowered 
into the basin, sump or lift station, 
check  the  system  by  filling  with 

liquid  and  allowing  the  pump  to 
operate  through  its  pumping 
cycle. The time needed to empty 
the  system,  or  pump-down  time 

along  with  the  volume  of  water, 
should be recorded.

Check Pump Rotation -

 Improper 

motor rotation can result in poor 
pump  performance  and  can 
damage the motor and/or pump. 

Check  rotation  on  three  phase 

units  by  momentarily  applying 
power and observe the "kickback". 

Cooling  Oil  - 

Anytime  the  pump  is 

removed from operation, the cooling 

oil  in  the  motor  housing  should  be 
checked  visually  for  oil  level  and 
contamination. To  check  oil,  set  unit 

upright. Remove pipe plug (34) from 
housing (3). With a flashlight, visually 

inspect  the  oil  in  the  housing  (3)  to 

make  sure  it  is  clean  and  clear,  light 

amber  in  color  and  free  from 
suspended  particles.  Milky  white  oil 

indicates  the  presence  of  water.  Oil 
level should be just above the motor 
when pump is in vertical position.

Oil Testing

Ÿ

Drain  oil  into  a  clean,  dry 

container by placing pump on it’s 
side, remove pipe plug (34), from 

housing (3).

Ÿ

Check oil for contamination using 

an  oil  tester  with  a  range  to  30 
kilovolts breakdown.

Ÿ

If  oil  is  found  to  be  clean  and 
uncontaminated 

(measuring 

above 15 kV breakdown), refill the 

housing.

Ÿ

If  oil  is  found  to  be  dirty  or 
contaminated (or measures below 
15  kV  breakdown),  the  pump 

must  be  carefully  inspected  for 
leaks  at  the  shaft  seal,  cable 

assembly,  square  ring  and  pipe 
plug,  before  refilling  with  oil.  To 
locate  the  leak,  perform  a 
pressure test.

1.

2.

5.

4.

3.

barmesapumps.com

Содержание 2BSE102SS

Страница 1: ...rsible Solids Handling Pumps IMPORTANT Read all instructions in this manual before operating or servicing a pump 2BSE SS 0 5 0 75 1 HP 1750 RPM 2BSE51SS 0 5 HP 2BSE72SS 2BSE73SS 2BSE74SS 0 75 HP 2BSE1...

Страница 2: ...associatedwithornearthepump T h i s p u m p i s n o t i n t e n d e d f o r u s e i n swimming pools or water installations where there is DANGER humancontactwithpumpedfluid Riskofelectric shock To re...

Страница 3: ...ctioninmotor Three phase NEMA B oil filled Requires overload protection to be included in controlpanel 18 661 6 687 2 165 2 FLANGE 9 763 12 637 6 5 4 875 12 937 11 8 3 FLANGE MODEL PART No HP VOLTS PH...

Страница 4: ...top of the motor housing or a minimum level of 10 inches above the basin floor Electrical Connections Power cable The power cable mounted to the pump must not be modified in any way except for shorten...

Страница 5: ...ll with new oil Insulation Test An insulation megger test should be performed on the motor Before the pump is put into service The resistance values ohms as well as the voltage volts and current amps...

Страница 6: ...ocks or 4 piece of pvc pipe to avoid resting unit on shaft 05 Service Pressure builds up extremely fast increase pressure by TAPPING air nozzle Too much pressure will damage seal DO NOT exceed 10 PSI...

Страница 7: ...r equivalent to shaft threads Screw impeller onto shaft hand tight while using a screwdriver in the slot at the end of the shaft to hold it stationary Rotate impeller to check for binding 12 Place gas...

Страница 8: ...POWER CORD 4x12 G T1 T7 T2 T8 T3 T9 T4 T5 T6 G L1 L2 L3 GREEN BLACK RED WHITE MOTOR LEADS Cable Motor Lead Number Green Green Black 1 and 7 Red 2 and 8 White 3 and 9 4 5 and 6 together Figure 4 T2 T3...

Страница 9: ...08 Repair Parts Figure 5 For Repair Part Please supply Model Number and Serial as shown on Name Plate and Part Description and Part Number as shown on Parts List barmesapumps com...

Страница 10: ...R 3 DISHARGE 1 HT200 22 HEX SOCKET CAP SCREWS 1 4 20UNC x 28 2 SS 304 23 V SHAPE RING 1 NBR 40 24 MECHANICAL SEAL 31 8 x 15 9 x 32 5 1 SiC SiC 25 ELLASTIC COLLAR 40 1 65Mn 26 ELLASTIC COLLAR 17 1 65Mn...

Страница 11: ...supply leads to ensure proper impeller rotation 11 Repair fixturesasrequiredtoeliminateleakage 12 Check pump temperature limits and fluid temperature 13 Replace portion of discharge pipe with flexible...

Страница 12: ......

Отзывы: