23. MEASURING AIR TEMPERATURE

RISE

Air temperature rise (supply air temperature minus
return air temperature) must be within allowable air
temperature rise range specified on furnace rating plate
and in Table 1.

You will need 2 thermometers with 1 degree resolution
capable of reading up to 200 degrees F.  Check
thermometers to make sure they agree, or compensate
accordingly.

Follow this procedure:

1. Open supply air registers and return air grilles.

Make sure the registers and grilles are free of
obstruction from rugs, carpets, drapes or furniture.

22. CONVERSION OF GAS INPUT BTUH

FROM HIGH TO LOW RATING

All the derated WG series units are produced with
maximum BTUH input orifices installed.  To field
convert input, a change to main burner orifices is
required.

NOTE: 

 

No change to air orifices is necessary.  A set
of low input orifices is shipped with every
unit.  They will be found packaged in a bag
behind the burner door.  Refer to the unit
rating plate to confirm the proper orifice size.
Proper installation of the orifices is detailed
as follows:

A. Shut off electrical supply to the unit.

B. Shut off gas supply to the unit.

C. Remove burner access panel.

D. Disconnect gas valve from gas supply piping.

E. Disconnect the two wires from the gas valve.

F. Remove the manifold assembly so that orifices are

now accessible and remove orifices.

G. Apply a modest amount of pipe compound to the

new orifices and screw them into the manifold.

H. To assemble burner reverse steps A through G.

2. Set balancing dampers in supply duct system.

3. Check duct work for obstructions or leaks.

4. Make sure filters are clean and in place.

5. Place one thermometer in supply air plenum

approximately 2 feet from furnace.  Locate
thermometer tip in center of plenum to ensure proper
temperature measurement.

6. Place second thermometer in return air duct

approximately 2 feet from furnace.  Locate
thermometer tip in center of duct to ensure proper
temperature measurement.

7. Set room thermostat on highest temperature setting.

Operate furnace 10 minutes.  Record supply air and
return air temperatures.

8. Calculate air temperature rise by subtracting return

air temperature from supply air temperature.

If air temperature rise is above the temperature
rise range on rating plate, furnace is overfired
or has insufficient airflow.  Check gas input
following the instructions in Section, “Checking
Gas Input Rate”.  If air temperature rise is still
above temperature rise range specified, more
heating airflow is needed.  Check duct work and
grilles to make sure all are properly sized.

If air temperature rise is below the temperature
rise range on rating plate, furnace is underfired
or has too much airflow.  Check gas input
following the instructions in Section, “Checking
Gas Input Rate”.  If air temperature rise is still
below temperature rise range specified, less
heating airflow is needed.  Adjust dampers or
grilles as needed.

After making adjustments, you must check air
temperature rise to verify that resulting air
temperature rise is within allowable range.  If
air temperature rise is still outside the
temperature rise range specified on rating
plate, check duct system design with a
qualified heating engineer.  It may be
necessary to re-size the duct work.  Recheck
air temperature rise after revising duct systems.

9. Set room thermostat to desired setting.

10. Remove thermometers and seal duct work holes.

NOTE:  Failure to seal holes could result in reduced

system performance.

       WARNING

Failure to follow these instructions could
create a hazard resulting in property damage,
bodily injury, or death.

Содержание WG242DA

Страница 1: ...INSTRUCTIONS AND THE REQUIREMENTS OF ALL GOVERNING CODES AND ORDINANCES FOR THE INSTALLATION LOCATION IT IS THE RESPONSIBILITY OF INSTALLER TO KNOW AND UNDERSTAND ALL OF THESE REQUIREMENTS FAILURE TO...

Страница 2: ...old Pressure Adjustment 26 20 Checking Gas Input Rate 26 27 21 Standard Orifice Sizing High Altitude Derate 28 22 Conversion of Gas Input BTUH From High to Low Rating 31 23 Measuring Air Temperature R...

Страница 3: ...iagrams 49 Figure 20 Fan Blade 51 Figure 21 Low NOx Insert 51 TABLES Table 1 Specifications WG24 36 Models 7 Table 1A Specifications WG42 60 Models 8 Table 2 Minimum Installation Clearances 17 Table 3...

Страница 4: ...47 4044 COPYRIGHT SEPTEMBER 2003 BARD MANUFACTURING COMPANY INC BRYAN OHIO 43506 USA Manufactured under the following U S patent numbers 5 485 878 5 002 116 4 924 934 4 875 520 4 4825 936 These public...

Страница 5: ...t n e V l a i c r e m m o C P 3 P V R C G W 5 P V R C G W g n i t a l u d o M y l l u F r e z i m o n o c E 1 E 3 M F I E G W 5 M F I E G W t l o V 0 3 2 r o t a l i t n e V y r e v o c e R y g r e n...

Страница 6: ...or CAN CGA B149 1 latest edition and the National Electrical Code ANSI NFPA 7 or CSA C22 1 latest edition It is the personal responsibility and obligation of the purchaser to contact a qualified inst...

Страница 7: ...2 0 3 2 8 0 2 0 3 2 0 6 4 s p m A d a o L d e t a R 5 0 1 5 9 6 6 2 6 3 3 5 3 1 5 2 1 5 9 0 9 5 6 1 4 1 0 1 5 9 5 t n e r r u C n o i t c e l e S t i u c r i C h c n a r B 5 0 1 7 6 5 3 1 4 1 5 9 5 6...

Страница 8: ...8 0 2 0 3 2 0 6 4 s p m A d a o L d e t a R 5 9 1 1 2 5 4 1 5 3 1 8 5 1 2 1 2 3 1 5 2 1 2 6 0 3 7 2 5 9 1 7 1 9 t n e r r u C n o i t c e l e S t i u c r i C h c n a r B 1 2 5 1 6 7 2 2 3 1 4 6 0 3 5...

Страница 9: ...TER HINGED DOOR COMBUSTION AIR EXHAUST COMBUSTION AIR INTAKE CONTROL LOW VOLTAGE ENTRANCES CIRCUIT BREAKER VENT OPTION MIS 2123 A UNIT A B C D E F G H I J K L M N O W G 24 W G 30 W G 3 6 7 88 27 88 13...

Страница 10: ...nd in the absence of specific recommendations from the local authority having jurisdiction equipment ratings shall be reduced as specified in Section 21 5 TRANSPORTATION DAMAGE All units are packed se...

Страница 11: ...ible wall use a minimum of Figure 1 A dimension plus 2 inches and B dimension plus 2 inches See Figures 4 and 5 for details 3 Locate and mark lag bolt locations and bottom mounting bracket location 4...

Страница 12: ...PTIONAL 12 FLANGE SCREWS UNIT SUPPORT 1 MIN NECCESSARY NO CLEARANCE SUPPLY AIR DUCT RETURN AIR DUCT CONTROL PANEL VESTIBULE DOOR WALL STRUCTURE OUTSIDE 1 CLEARANCE ON ALL FOUR SIDES OF SUPPLY AIR DUCT...

Страница 13: ...Manual 2100 376L Page 13 of 81 FIGURE 2A MOUNTING INSTRUCTIONS FOR WG42 WG48 AND WG60...

Страница 14: ...of one 1 inch clearance must be maintained between the supply air duct and combustible materials This is required for the first three 3 feet of ducting It is important to insure that the one 1 inch m...

Страница 15: ...Manual 2100 376L Page 15 of 81 FIGURE 4 WALL MOUNTING INSTRUCTIONS FIGURE 5 WALL MOUNTING INSTRUCTIONS...

Страница 16: ...Manual 2100 376L Page 16 of 81 FIGURE 6 COMMON WALL MOUNTING INSTALLATIONS...

Страница 17: ...ed air from the condenser to recirculate to the condenser inlet TABLE 2 MINIMUM INSTALLATION CLEARANCES s l a i r e t a m e l b i t s u b m o c m o r f t c u D t e l t u O t e e f 3 t s r i f h c n i...

Страница 18: ...ncludes a stainless steel transition drain tee silicone sealant and drain tubing If unit is installed with vertical vent kit annually inspect the vent system and drain Replace any portion of the vent...

Страница 19: ...nce spillage at the draft hood relief opening after 5 minutes of main burner operation Use the flame of a match or candle 6 After it has been determined that each appliance connected to the venting sy...

Страница 20: ...electrical ground could result in electric shock or fire 15 WIRING MAIN POWER Refer to unit rating plate for wire sizing information and maximum fuse or HACR type circuit breaker size Each outdoor uni...

Страница 21: ...mary voltage transformers and no rewiring is required TABLE 3 THERMOSTAT WIRE SIZE r e m r o f s n a r T A V A L F e g u a G e r i W m u m i x a M e c n a t s i D t e e F n I 5 5 3 2 e g u a g 0 2 e g...

Страница 22: ...Manual 2100 376L Page 22 of 81 FIGURE 11 LOW VOLTAGE WIRING...

Страница 23: ...Manual 2100 376L Page 23 of 81 FIGURE 11A LOW VOLTAGE WIRING...

Страница 24: ...Manual 2100 376L Page 24 of 81 FIGURE 12 GAS PIPE CONNECTION...

Страница 25: ...c foot test dial and allowing 4 minutes to show any movement and by soaping each pipe connection and watching for bubbles If a leak is found make the necessary repairs immediately and repeat the above...

Страница 26: ...kits may be purchased from your local distributor 5 Slowly open equipment shut off valve in gas supply line just ahead of furnace Start furnace following Operating Instructions on front door 6 Slowly...

Страница 27: ...the furnace gas input 9 If you left water heater dryer or range pilots on allow for them in calculating correct furnace gas input A quick way is to allow 1 000 BTU per hour for a water heater 500 BTU...

Страница 28: ...5 7 0 6 0 0 5 7 6 6 0 8 8 5 0 4 3 5 6 2 6 8 6 5 0 8 1 3 6 8 1 9 4 5 0 2 0 1 6 0 6 4 3 5 0 0 4 9 5 8 8 4 2 5 0 2 3 8 5 3 7 2 1 5 0 7 9 6 5 4 4 5 0 5 0 6 1 6 5 2 7 5 9 4 0 8 0 5 5 5 6 9 8 4 5 0 4 4 5 4...

Страница 29: ...F 0 0 0 0 1 o t 1 0 0 8 h c t i w S e r u s s e r P s e r i u q e R e g n a h C e c i f i r O d n a e g n a h C t n e t n o C U T B n o d e s a B U T B 0 5 2 0 2 r e n r u B r e P 9 4 7 0 0 7 0 6 2 0...

Страница 30: ...r e d 0 1 l a n o i t p o l a n o i t p O d l e i F 0 1 d e t r e v n o C e t a r e D t a e H s a G e u l a V t F u C U T B o N t e e F 0 0 0 6 o t p U t p e c x E s e g n a h C t n e t n o C U T B r...

Страница 31: ...ximately 2 feet from furnace Locate thermometer tip in center of plenum to ensure proper temperature measurement 6 Place second thermometer in return air duct approximately 2 feet from furnace Locate...

Страница 32: ...d Feature If the high pressure switch opens the compressor contactor will de energize immediately The lockout timer will go into a soft lockout and stay in soft lockout until the high pressure switch...

Страница 33: ...ke DOM timing on power up and after power interruptions is equal to 2 minutes plus 10 of Delay on Break DOB setting 0 5 minute 30 seconds DOB 123 second DOM 1 0 minute 60 seconds DOB 126 second DOM 2...

Страница 34: ...Manual 2100 376L Page 34 of 81 26 LIGHTING AND SHUTDOWN INSTRUCTIONS FIGURE 15 INSTRUCTION LABEL...

Страница 35: ...ht on small mirror or an extension handle Remove the screws securing the inducer and collector box Now inspect the upper tubes of the heat exchanger Check the exterior of the heat exchanger and the in...

Страница 36: ...sure the supply and return air flange sleeves or duct work are securely fastened to unit and physically sound d Supply and return grilles must be open and free from obstructions e Inspect to make sur...

Страница 37: ...speed blower relay will be energized as well as the compressor contactor Following termination of the cooling cycle the blower motor will continue to run for one minute See Figure 17 for additional i...

Страница 38: ...s n i g e b g n i m i t y a l e d f f o n a f t a e H d e z i g r e n e e d l o o c r o f l l a c s n i g e b t a t s o m r e h T d e z i g r e n e e r s l a n i m r e t Y d n a G d e z i g r e n e s...

Страница 39: ...f it is desirable to have both HEAT COOL blower motor speed at the same speed install a jumper wire between HEAT and COOL terminals of the integrated furnace control board and place both unused motor...

Страница 40: ...0 7 0 2 1 1 0 2 1 1 0 4 9 4 0 0 9 7 0 3 0 1 0 3 0 1 0 6 8 5 0 0 1 9 0 1 7 0 5 9 6 0 0 0 8 0 4 8 P S E s e h c n I H2 O E D O M G N I L O O C E D O M G N I T A E H d n a N A F L A U N A M l i o C t e W...

Страница 41: ...0 8 7 6 0 0 4 9 0 8 9 0 4 8 0 6 6 0 8 9 0 4 8 0 6 6 P S E s e h c n I H2 O E D O M G N I L O O C E D O M G N I T A E H d n a N A F L A U N A M l i o C t e W t u p n I U T B 0 0 0 8 6 t u p n I U T B...

Страница 42: ...1 0 3 0 1 0 9 1 1 0 3 0 1 0 6 8 5 0 0 5 0 1 0 9 0 1 0 5 9 0 9 0 1 0 5 9 6 0 0 4 9 0 8 9 0 8 9 0 4 8 P S E s e h c n I H2 O E D O M G N I L O O C E D O M G N I T A E H d n a N A F L A U N A M l i o C...

Страница 43: ...3 1 1 0 3 4 1 0 3 1 1 P S E s e h c n I Hs O E D O M G N I L O O C N A F L A U N A M d n a E D O M G N I T A E H l i o C t e W U T B 0 0 0 0 0 1 t u p n I U T B 0 0 0 0 9 h g i H m u i d e M w o L h g...

Страница 44: ...0 4 3 1 0 3 4 1 0 3 4 1 0 3 1 1 P S E s e h c n I Hs O E D O M G N I L O O C N A F L A U N A M d n a E D O M G N I T A E H l i o C t e W U T B 0 0 0 0 0 1 t u p n I U T B 0 0 0 0 9 h g i H m u i d e...

Страница 45: ...3 1 0 3 4 1 0 3 4 1 0 3 1 1 P S E s e h c n I Hs O E D O M G N I L O O C N A F L A U N A M d n a E D O M G N I T A E H l i o C t e W U T B 0 0 0 0 0 1 t u p n I U T B 0 0 0 0 9 h g i H m u i d e M w...

Страница 46: ...c e l e s e h t r o f e t a r e p o l l i w r e w o l b r i a t r o f m o c e h t e t a r e p o o t e u n i t n o c l l i w r e w o l b r i a t r o f m o c e h t n o i t a r e p o S T I N U Y T E F A...

Страница 47: ...oling call CR3 This relay terminates the signal to the Dehumidification Solenoid and also the Y signal to the CCM during a call for Heat TDR1 This time delay relay is a 10 second Delay On Break device...

Страница 48: ...8 6 2 3 2 8 6 4 3 3 8 6 6 3 B D g e d 0 8 B W g e d 7 6 e d i S w o L e d i S h g i H 7 7 8 2 2 9 7 5 4 2 1 8 2 6 2 2 8 9 7 2 4 8 8 9 2 5 8 6 1 3 7 8 5 3 3 8 8 5 5 3 9 8 5 7 3 B D g e d 5 8 B W g e d...

Страница 49: ...s into a FIGURE 19 CIRCUIT DIAGRAMS AIR CONDITIONING MODE CIRCUIT DIAGRAM separate desuperheating condenser circuit which reheats the conditioned air before it is delivered to the room The refrigerant...

Страница 50: ...3 9 5 9 2 4 9 3 1 3 6 9 3 3 3 8 9 5 5 3 0 0 1 8 7 3 2 6 3 G W B D g e d 5 7 B W g e d 2 6 e d i S w o L e d i S h g i H 2 7 2 2 2 4 7 8 3 2 5 7 5 5 2 6 7 2 7 2 8 7 0 9 2 9 7 8 0 3 1 8 6 2 3 2 8 6 4 3...

Страница 51: ...regulations for nitrogen oxide emission levels Refer to Figure 21 for NOx insert information IMPORTANT For propane LP conversions the NOx reduction screen inserts shown below must be removed This is a...

Страница 52: ...ICATION DATA FOR WG30 DA s n o i t i d n o C r o o d n I r o o d t u O t n e i b m A y t i c a p a C m e t s y S s d n u o P r e t a W r H s b L w o l f r i A M F C x o r p p A y l p p u S r i A B W B...

Страница 53: ...n in are BTUH of heating available at these conditions Latent BTU Lbs Hr water 1060 Sensible BTU Total Latent Values shown in are BTUH of heating available at these conditions Latent BTU Lbs Hr water...

Страница 54: ...APPLICATION DATA FOR WG60 DA s n o i t i d n o C r o o d n I r o o d t u O t n e i b m A y t i c a p a C m e t s y S s d n u o P r e t a W r H s b L w o l f r i A M F C x o r p p A y l p p u S r i A...

Страница 55: ...3 0 3 G W 3 5 3 5 8 0 4 6 6 A 4 5 3 5 8 0 4 7 6 A D 2 6 3 G W A 9 3 1 5 8 0 4 8 6 A 7 3 1 5 8 0 4 7 5 B D 2 6 3 G W A 9 3 2 5 8 0 4 9 6 A 7 3 2 5 8 0 4 9 5 C D 3 6 3 G W 5 5 3 5 8 0 4 0 7 A 0 6 3 5 8...

Страница 56: ...Manual 2100 376L Page 56 of 81 WG242DA 230 208 60 1...

Страница 57: ...Manual 2100 376L Page 57 of 81 WG242DA WG362DA 230 208 60 1...

Страница 58: ...Manual 2100 376L Page 58 of 81 WG242DB 230 208 60 3...

Страница 59: ...Manual 2100 376L Page 59 of 81 WG242DB WG362DB 230 208 60 3...

Страница 60: ...Manual 2100 376L Page 60 of 81 WG243DC 460 60 3...

Страница 61: ...Manual 2100 376L Page 61 of 81 WG243DC 460 60 3...

Страница 62: ...Manual 2100 376L Page 62 of 81 WG302DA 230 208 60 1...

Страница 63: ...Manual 2100 376L Page 63 of 81 WG302DA WG482DA WG602DA 230 208 60 1...

Страница 64: ...Manual 2100 376L Page 64 of 81 WG302DB 230 208 60 3...

Страница 65: ...Manual 2100 376L Page 65 of 81 WG302DB WG482DB WG602DB 230 208 60 3...

Страница 66: ...Manual 2100 376L Page 66 of 81 WG303DC 460 60 3...

Страница 67: ...Manual 2100 376L Page 67 of 81 WG303DC 460 60 3...

Страница 68: ...Manual 2100 376L Page 68 of 81 WG362DA 230 208 60 1...

Страница 69: ...Manual 2100 376L Page 69 of 81 WG362DB 230 208 60 3...

Страница 70: ...Manual 2100 376L Page 70 of 81 WG363DC 460 60 3...

Страница 71: ...Manual 2100 376L Page 71 of 81 WG363DC 460 60 3...

Страница 72: ...Manual 2100 376L Page 72 of 81 WG423DA 230 208 60 1...

Страница 73: ...Manual 2100 376L Page 73 of 81 WG423DA 230 208 60 1...

Страница 74: ...Manual 2100 376L Page 74 of 81 WG423DB 230 208 60 3...

Страница 75: ...Manual 2100 376L Page 75 of 81 WG423DB 230 208 60 3...

Страница 76: ...Manual 2100 376L Page 76 of 81 WG424DC 460 60 3...

Страница 77: ...Manual 2100 376L Page 77 of 81 WG424DC 460 60 3...

Страница 78: ...Manual 2100 376L Page 78 of 81 WG482DA WG602DA 230 208 60 1...

Страница 79: ...Manual 2100 376L Page 79 of 81 WG482DB WG602DB 230 208 60 3...

Страница 80: ...Manual 2100 376L Page 80 of 81 WG483DC WG603DC 460 60 3...

Страница 81: ...Manual 2100 376L Page 81 of 81 WG483DC WG603DC 460 60 3...

Отзывы: