background image

  

Stationary VRLA Batteries, 

 

Installation and Operation Instructions 

Page 9 of 16 

w w w. b a e b a t t e r i e s u s a . c o m 

R e v :   0 2 1 9

 

 

All bolted connections should be made using a calibrated torque wrench to insure proper 
tightness of the connection without causing any damage to the battery posts.  The torque 
settings for the BAE M10 Allen bolt is: 

 

22 Newton-meters or 195 (194.7 actual) inch-pounds.   

6.5  TERMINAL PLATES 

For multi-terminal cell strings, terminal plate assemblies are provided standard for the +/- 
customer connection cells.  For single terminal cell strings the terminal plates are 
purchased as an optional item.  The terminal plates allow for customer connection with 
either single hole or 2-hole 3/8” lugs with 1” spacing. 

These terminal plate assemblies are to be bolted together using the following torques for 
the terminal plate/bracket connection and the bracket to battery post connection.  
Terminal plate covers are included as part of the terminal plate kit for safety. 

  

For horizontal cell mount modules and racks, the terminal plate assemblies may be 
provided as part of the system and may be mounted on the racks and not the battery 
terminals themselves.  The specific rack/module configuration will have to be checked to 
determine proper terminal plate mounting. 

6.6  FINAL INSTALLATION STEPS 

Once the cells have been installed and the connections completed, the following items 
should be considered. 

  Clean the battery room with all installation debris being removed. 

  Once the battery room has been cleaned, all of the cells should be wiped down and 

cleaned using a damp cloth – dampen the cloth with clear (distilled) water.  See 
Section 9.1 on cleaning of cells.   

 

NOTE:  

DO NOT use cleaners or chemicals to clean the cells without prior written 

approval from BAE.  

 

  Once the cells have been thoroughly cleaned, apply the supplied cell numbering 

stickers to the upper left or right hand corner of the face of the cells as desired.   

o

  Please note the cells should always be numbered from the most positive cell to 

the most negative cell. 

Connection 

Type 

Torque setting for 
BAE SS Hardware 

N-m (in-lbs) 

Angle Bracket to 

Battery Post 

22 N-m (195 in-lbs) 

Terminal Plate to 

Angle Bracket 

28 N-m (247 in-lbs) 

Содержание OPzV Series

Страница 1: ...STATIONARY BAE BATTERIES Valve Regulated Lead Acid VRLA Installation and Operating Instructions OPzV OGiV Series Batteries Important Documents Do Not Discard...

Страница 2: ...rks as explosion and fire hazards exist Acid splashes on the skin must be flushed with plenty of water Acid splashes in eyes must be flushed thoroughly for at least 15 minutes with plenty of water See...

Страница 3: ...2 ELECTRICAL HAZARDS A filled and charged battery presents a high voltage high current shock and short circuit hazard PRECAUTIONS Observe standard safety measures when working on batteries a Remove w...

Страница 4: ...ING RACK 6 5 2 RACKS NEW RACK 7 6 0 BATTERY CELL JAR INSTALLATION 7 6 1 INSTALLATION ON RACKS VERTICAL MOUNT 7 6 2 INSTALLATION ON RACKS HORIZONTAL MOUNT 8 6 3 TERMINAL PREPARATION 8 6 4 INTER CELL CO...

Страница 5: ...2 CONCEALED DAMAGE It is recommended that the cells be unpacked and checked for concealed damage as soon as possible Freight carriers generally require that concealed damage be inspected by the carrie...

Страница 6: ...w BAE VLA batteries have a specific gravity of 1 240 kg l at 68 F Specific Gravity 68 F Freezing point Specific Gravity 68 F Freezing point C F C F 1 000 0 0 32 0 1 225 39 8 39 0 1 150 15 1 5 0 1 250...

Страница 7: ...size and type of cell and the intended application of the battery Standard designs provide for installation in battery cabinets conventional vertical mount steel racks horizontal mount racks for some...

Страница 8: ...d allow the rack to shift or collapse If the new rack is not designed for the new batteries being installed this could affect your seismic rating and battery warranty Please contact BAE USA or your lo...

Страница 9: ...instructions This is a separate BAE Batteries USA instruction document Important For horizontal racks with battery rails instead of module shelves please be sure the lip between the jar and cover is...

Страница 10: ...modules and racks the terminal plate assemblies may be provided as part of the system and may be mounted on the racks and not the battery terminals themselves The specific rack module configuration w...

Страница 11: ...safety signs are present and installed properly for the battery room Additionally please ensure the proper Personal Protection Equipment PPE spill containment or cleanup kit and eyewash are present wi...

Страница 12: ...etween 10 C 50 F and 30 C 86 F Total string float voltage will be 2 25 V x number of cells 1 nominal Higher or lower charging voltages can be detrimental as overcharging or undercharging will reduce t...

Страница 13: ...re of 8 4 C 15 F over the 25 C 77 F norm would double the corrosion rate thus this reduces battery life to 50 of the normal life expectancy A further increase of 16 7 C 30 F over the 25 C 77 F norm wo...

Страница 14: ...ility of the battery system The periodic inspections listed below are the minimum required For additional guidance on recommended battery maintenance reference IEEE 1188 To be measured and recorded Qu...

Страница 15: ...If float current is used to determine state of charge it is important that this value be measured accurately Float current of a fully charged cell under normal conditions is typically 20 to 30 mA per...

Страница 16: ...y test it is helpful to take into account the operating conditions and specific site requirements From this select a discharge time and current or power that best fits the requirements these values ar...

Страница 17: ...that you contact BAE USA or your local representative It is generally recommended that if the measured capacity of the battery is less than 80 the battery should be considered for replacement 11 0 9...

Отзывы: