Preparing the Gas Analysis System for Use
with flow conditioner
9 x pipe Ø
2 x pipe Ø
Recommendation for a Setup with an Extension in the Inlet or Outlet Section
< 150mm
>= 150mm
with flow conditioner
20 x pipe Ø
15 x pipe Ø
9 x pipe Ø
10 x pipe Ø
5 x pipe Ø
2 x pipe Ø
(E)
Recommendation for a Setup with a Reduction in the Inlet or Outlet Section
< 150mm
>= 150mm
with flow conditioner
15 x pipe Ø
10 x pipe Ø
6 x pipe Ø
5 x pipe Ø
3 x pipe Ø
1 x pipe Ø
5.2.8
Initial Operation
Prior to the initial operation of the gas analysis system, it needs to be checked whether the operating
conditions comply with the guidelines provided in this manual. When starting up the process analysis
system, the following points have to be noted:
–
The gas analysis system has to be fully installed and connected.
–
Start up the gas analysis system only in an acclimatized state.
–
Connect the appropriate gas analysis systems to the main power supply and use the main switch
to turn them on.
32