MAN - PAV4 - REV: Original | F. Operation
23
F. Operation
The process below assumes that the PAV has been standardized, air pressure has been attached to the PAV and
that the system is ready to run test cycles.
1. Turn the power switch on the front of the PAV to the ON position. The HMI display will power on. The status display
will show “Off”.
2. Select “View” on the HMI Main screen.
3. Select “Settings” on the HMI View screen.
4. Verify that all the parameters are set correctly for your application.
5. Select “Done” to return to the View Screen.
6. Select “Done” to return to the Main Screen.
7. Open the oven lid by unlatching the latches. Unbolt (see note below) and open the vessel lid, Insert an EMPTY pan
holder into the PAV vessel.
NOTE: DO NOT load any samples into the PAV at this time.
NOTE: Bolt 1 in the diagram is a pivot bolt and should only be loosened to allow the vessel lid to
slide open and rest on the support block and to slide closed. This bolt should NOT be removed.
Forcing this bolt may damage the bolt assembly.
Figure F.1 - Bolt 1