INSTRUCTIONS FOR THE PUTTING INTO SERVICE AND USAGE OF THE MA-
CHINERY
COMMISSIONING
After obtaining of the machine and before putting it in into service, it is important to adhere strictly to the instructions given
below in Before starting.
Make sure that the operating personnel read and understand the rules and follow the instructions given in this handbook
before the machine operation or maintenance.
Before towing of the machine, make sure the tyre pressures are correct (see chapter Drawings, diagrams, descriptions
and explanations on page 4 ) and that the handbrake works properly (see chapter Description of the adjustment and
maintenance operations on page 30 ). Before towing of the machine in reduced visibility conditions, make sure that the lights
work properly (where installed).
Make sure all packaging and transport materials are removed.
Make sure that the correct tow hitch, lifting or binding devices are used when the machine is transported or lifted.
When choosing the working position of the machine, be sure that there is sufficient ventilation system for cooling and exhaust
fumes and required minimal working space is observed (wall, ceiling, etc.).
Adequate clearance needs to be allowed around and above the machine to permit safe access for operation and maintenance.
The air inlet should be secured against any free objects sucked into it.
Make sure that the machine is positioned on a stable foundation. Any risk of movement should be removed by suitable
means, especially it is necessary to avoid straining of outlet piping system.
Attach the battery cables to the battery clamps and tighten them securely. Attach the positive pole (+) cable before attaching
the negative pole (-) cable.
Warning
Nominal pressure of all air pressure equipment installed in or connected to the machine must be equal or
greater than nominal pressure of the machine. All materials used must be compatible with the compressor oil
(see chapter Drawings, diagrams, descriptions and explanations).
Warning
If more than one compressor are connected to one common air pressure equipment simultaneously, make sure
back pressure valves and control valves are installed, so that one machine cannot accidentally be pressurised /
over pressurised by another.
Warning
If flexible discharge hoses carry more than 7 bar pressure then it is recommended that safety binding is used on
the hoses ends.
BEFORE STARTING
1. Install the machine on a level floor (max. allowed slope in longitudinal and transverse axis is 15
∘
) and secure it against
movement (pull the handbrake, use wedges).
2. Check the engine oil level according to the instructions in the handbook.
3. Check the separator oil level. Check there is no leaking in the oil circuit. Check that all outlet plugs and a filling nozzle
of the separator vessel are tightened.
4. Check the coolant level (the machine is positioned horizontally).
5. Check the fuel filter (opt. drain water so that the filter contains only fuel).
6. Check the diesel oil level in the fuel tank.
7. Check the air filter indicator. (see chapter Description of the adjustment and maintenance operations on page 30 ).
17
At 2020/N
X.11.2016