Detail in Fig. 1.
Must be
accurate.
120mm from
top of wall channel to
top of end connector
channel.
10.
Apply plastic packers
(bag11)into the base
glazing channels in
locations as shown.
11.
CRITICAL SEAL
Remove dust and dirt first. Seal the connection
between the glass receiver channel and the base
glazing channel
with clear silicon
prior to the
installation of
panel
SL R.
Ensure the corner junction between wall channel
and base channel is full of silicon before final glass
placement. It is vital
that all junctions are
sealed sufficiently.
Prior to installation of
glass panels and infill all
connections
of channels, must be
sealed with clear silicon
supplied
12.
Locate the glass panel
SL R
into the glazing
channel. The top
of panel
SL R
must be level with
the top of the
glass receiver
channel on the
door side. Adjust
height of panel if
necessary by
adding or
removing plastic
packers (bag11) in
the base glazing
channels.
13.
TOP RAIL BRACE INSTALLATION
It is recommended
that the top rail
brace is fitted prior
to tiling. AVOID
SCRATCHING.
Trim to length if
necessary. Slide into
the end connector
channels. The hole
for the adjusting block should be positioned
towards the top of the bar. Drill into CSK holes
provided in end connector channel. Fix with the
short CSK screws.
Ensure the top rail brace is level. Drill into CSK
holes provided in the end connector channel. Fix
with the short
CSK screws.
(bag103SL
–
preferably
hand screw)