background image

11

12

The emergency stop button immediately disconnects the inverter from both grid and 
battery,  which  ensure  the  safety  of  the  inverter.  By  pressing  the  emergency  stop 
button, the device will be locked in the "off" position. Only release the emergency 
stop  button  by  rotating  it  clockwise  and  closing  AC,  DC  breaker,  can  the  inverter 
resume working normally.

Figure 3-3-1-4 Off-on knob

It  displays  the  inverter’s  operating  parameters,  power  generation,  and  faulty 
information record. Please refer to Section 6, for details.

Off-on knob

It is used to start or stop the inverter.

Touch screen

3.4.1 ON-grid charge and discharge mode

3.4. Operation mode

There are several operation modes of the inverter.

CAUTION

When the ambient temperature is too high, it is normal the inverter 
reduces  the  output  power.  However,  if  this  frequently  happens, 
check  the  cooling  surface  of  the  inverter  or  place  the  inverter  in 
better ventilation conditions place. If the inverter fan is dirty, please 
clean  the  fan,  if  there  is  problem  with  the  inverter  internal 
electrical, please seek help from professional services.

3.4.3 Fault mode

When  the  DC  power  system  fails,  the  inverter  will  immediately  disconnect  the  AC 
contactor  and  enters  into  the  fault  mode,  so  as  to  ensure  the  safety  of  the  system. 
Inverter continuously monitors fault status and will not enter charge and discharge 
mode until the fault is eliminated.

3.4.4 Permanent fault mode

When  the  DC  power  system  is  in  serious  failure,  the  inverter  will  immediately 
disconnect  the  AC  contactor  and  enters  into  the  Permanent  fault  mode,  so  as  to 
ensure  the  safety  of  the  system.      For  example:  inverter  module  failure  etc.  please 
contact  your  local  dealer  or  ATESS  directly  when  inverter  enters  permanent  fault 
mode, repairmen on site is not allowed without authorization of ATESS.

Working procedure of PCS100 at on-grid charge and discharge mode:

1) PCS100 connected to battery on the DC side, and grid on the AC side;

2) Close the ac/dc circuit breaker and start-stop knob, PCS100 enter waiting status;

3)  Start  PCS100  via  the  LCD,  it  will  start  self-checking,  once  it  fulfills  on-grid 
conditions, the energy storage controller will run in "on-grid charge“mode.

4) Click the "switch" button on the screen. You can complete the battery charge and 
discharge state transitions. Charge current and discharge power can be set(default 
20A charge, full power discharge).

3.4.2 Off-grid charge and discharge mode

At  off-grid  mode,  PCS100  can  work  automatically,  the  inverter  will  sense  the  load 
power and adjust its output automatically :

1) PCS100 connected to battery on the DC side, and load equipment on the AC side, 
make sure grid is not connected;

2) Close the AC/DC circuit breaker and start-stop knob, PCS100 enter waiting status;

3) Start PCS100 via the LCD, inverter starts self-check, when self-check finished and 
meet working requirement, inverter connects to local load.

4) inverter senses load power and adjust its output to supply local load equipment.

Содержание PCS100

Страница 1: ... User Manual GR UM 053 A 01 Shenzhen ATESS Power Technology Co Ltd 86 755 2998 8492 www atesspower com T W 1st Floor of Building 3 at Sector B and 3rd Floor of Building 9 Henglong Industrial Park No 4 Industrial Zone Shuitian 86 755 2998 5623 F ...

Страница 2: ...3 7 Storage 3 8 Dimension 3 9 Packaging information GUI instruction 6 Pilot operation 5 2 Inspection 5 4 Pilot operation completion 5 3 Power on steps 5 1 Relevant requirements 5 5 5 Power off steps 6 1 LCD display screen introduction 6 2 LCD operation 6 3 LCD display information schedule Routine maintenance 7 7 1 Replacing the dust screen 7 2 Regular maintenance Products installation 4 4 2 Tools ...

Страница 3: ... professional electricians or professionally qualified personnel can transport or install this product 2 The operator should be fully familiar with the structure and working principle of the entire Energy Storage system 3 The operator should be fully familiar with this manual 4 The operator should be fully familiar with the local standards of the project Qualification 1 3 How to use this Manual Re...

Страница 4: ...for qualified electrical technician only When inverter operating don t touch any electrical parts except for the touch screen All electrical operation must comply with local electrical operation standards Warranty service for the inverter does not contain module maintenance Permission from the local utility company is required before installing the Energy Storage system and only professional perso...

Страница 5: ...ast 5 minutes Only professional technical personnel are qualified for the operation Maintenance and modification Only personnel with ATESS authorization are qualified for the maintenance and modification And to ensure personal safety use original accessories provided by the manufacturer only Otherwise electrical safety and EMC might not comply with the required standard Function and safety paramet...

Страница 6: ...lation tools or other unnecessary items are not left inside the inverter before starting up Item 4 Maintenance notice Maintenance can only be carried out after the inverter totally discharged Product description 3 ATESS PCS100 bidirectional battery inverter is designed for energy storage system it converts DC current generated by battery bank into AC current and feed it into the load grid also it ...

Страница 7: ...event dust from entering into the inverter Figure 3 3 1 Part description There are two LED indicators on the inverter which is used to display the current status of the inverter Figure 3 3 1 2 LED indicators LED Description POWER The indicator lights when power supply to the inverter is normal FAULT The indicator lights when power supply to the inverter is normal Figure 3 3 2 LED status Indicator ...

Страница 8: ... eliminated 3 4 4 Permanent fault mode When the DC power system is in serious failure the inverter will immediately disconnect the AC contactor and enters into the Permanent fault mode so as to ensure the safety of the system For example inverter module failure etc please contact your local dealer or ATESS directly when inverter enters permanent fault mode repairmen on site is not allowed without ...

Страница 9: ...perature range 40 55 Storage relative humidity range 5 95 Operating temperature range 25 55 Operating relative humidity range 5 95 Max altitude 2000 m 3 6 Protection Anti islanding When the local power grid shutdown due to malfunction or maintenance of equipment the inverter will be physically cut off the connection to the grid in order to protect operating personnel working in the electricity gri...

Страница 10: ...et and bottom outlet Cable trenches are recommended The cable trenches are often designed and constructed by the construction side based on relevant standards with the equipment weight and dimensions required to be considered Good electrical connection is needed between different cable trenches and GND terminals Wiring specification Cables in the inverter can be classified into either power cables...

Страница 11: ...pare parts required for whole machine installation Tools and spare parts required for installation is as follows Hoisting crane forklift or fork lift truck with the capacity for bearing the weight of the inverter Torque wrench Screwdriver Wire stripper Terminal crimping machine Heat dryer Megger and multimeter Before the inverter is moved to the designated place we suggest to lay the DC input cabl...

Страница 12: ...inet of the equipment according to the following procedures Procedure 1 Demolish the wood side and roof of the packaged cabinet Procedure 2 Demolish the out set package material on the machine Procedure 3 Demolish the fastening screws between the machine and the pallet Demolish the front and back cover lids of the pedestal Screw off the hold down nuts at the bottom of the wood pallet Remove the sc...

Страница 13: ...ils and the grid is three phase grid Meanwhile it shall be permitted by local power supply department before install Grid connected inverted power Model ATESS PCS100 Grid Voltage Limit Grid Frequency Limit 360Vac 440Vac 45Hz 55Hz 55Hz 65Hz Cable Cu Cable Diameter Requirements mm Model ATESS PCS100 3 Cable requirements Aperture DC Φ10 30N m DC Grid Phase A 2 1 input cables with each at least 70 mm ...

Страница 14: ...sitive and negative with a multimeter 3 Connect the positive of the battery to the DC of DC input 4 Connect the negative of the battery to the DC of DC input 5 Please be sure that all wirings are fastened Figure 4 4 3 DC Input Wiring 4 4 4 AC side wiring CAUTION Caution risk of danger When connecting the AC grid cut off the circuit breaker at the AC side to ensure that the AC wire connecting to te...

Страница 15: ...he user needs to monitor the operating status of DC power generation system we provide single machine and multi machine control programs and diversified communication interfaces for customer s selection 4 5 1 RS485 communication The inverter through RS485 tandem is connected with the PC for communication through RS485 RS232 adaptor Inside the PC a multi machine monitoring software ShineNet indepen...

Страница 16: ...ion Inspection List Pilot operation 5 The chapter will introduce the procedure of pilot operation including checking battery voltage input and output connecting other preparation working 5 1 Relevant requirements Before pilot operation the installation conditions of the equipment shall be examined thoroughly in particular whether voltages at DC and AC ends are consistent with inverter s requiremen...

Страница 17: ...power off In operation process of the inverter it can be powered off by clicking OFF button on the screen At this moment the inverter stops working CAUTION After manual power off the machine must be powered on manually otherwise the inverter is unable to power on 5 4 Pilot operation completion The following procedures shall be carried out after the inverter is normally in operation Procedure 1 Ins...

Страница 18: ...unication state station number and system time is displayed at the top of each page of the LCD Each page has five commonly used function keys run data historical information system settings Home at the below of the page The five commonly used keys corresponding sub menu are under the button and it will be marked green after selected 6 2 1 Home page Clicking Home button in any interface will enter ...

Страница 19: ... default language is Chinese Time settings system time setting if the date and time displayed on LCD is not inconsistent with the actual date and time they can be modified here Device Information This page shows the manufacturer inverter serial number hardware and software version information and the date of manufacturing Maintenance the interface requires a password to login It is for electrician...

Страница 20: ...the corresponding sub menu interface The default interface is the real time data interface Insert USB Disk on the back of the LCD display and the real time operation data will be stored in the USB Disk in every minute Inverter will create a CSV format file every month in the USB disk for data storage Real time data current DC power generation parameters and real time data including the grid voltag...

Страница 21: ...lt_Fault AC_UV_UnderVolt_Fault No information 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 AC_GridCurr_DcHigh_Fault AC_GridCurr_High_Fault AC_L_Curr_High_Fault AC_Overload_Fault Smoke_Alarm_Fault GFDI_HallSense_Fault GFDI_AirSwitch_Fault Inductor_Rly_Fault LVRT_Fault Module1_OverTemp_Fault Module2_OverTemp_Fault...

Страница 22: ...ust screen replacement 1 The front and back cover can be seen after opening the front and back cover of the inverter 2 Open front and back dust cover from the bottom of the dust cover 3 Take away the dust screen and insert a clean one 4 Place the dust cover in the original place and fix it Figure 7 1 Dustproof device No information 85 86 87 88 89 Batt_UnderVolt_Warning AC_WU_OverVolt_Rmt_Warning A...

Страница 23: ...C and DC disconnected for at least 5 minutes in order to avoid electric shock 7 2 Regular maintenance The inverter will not cause environmental pollution since the all the components meet the requirements of environmental protection According to environmental protection requirements user shall dispose the inverter in accordance with the relevant laws and regulations Appendix 8 VMAX DC absolute max...

Страница 24: ...any inverter which has been subjected to Misuse abuse neglect or accident Alteration improper installation or application Unauthorized modification or attempted repairs Insufficient ventilation of the product Transport damage Breaking of the original manufacturers seal Non observance of ATESS installation and maintenance instruction Failure to observe the applicable safety regulations Power failur...

Отзывы: