into the rivet body. This will require a firm push, the mushroom is fully seated once the base of 

the mushroom head is flush with the cover.

If not already in place, fit the horizontal waste plug operating rod so that the opposite end from 

the ball passes through the lower slot in the plastic cover and then through the clamp on the 

vertical operating rod.

Secure the horizontal rod by tightening the knurled nut onto the relevant fitting on the waste 

assembly fitted to the basin, do not over tighten.

Working through the aperture in the base of the cover, support the waste assembly, fit the nut 

and seals fitted to the P trap through the front hole in the cover and then connect to the P trap 

Connect the P Trap to the underside of the basin.

Fit the free end of the flexible hose to the waste pipe fitted to the site as part of the pre 

installation preparations. Secure the waste with a cable tie as shown in diagram on the previous 

page.  

Rod
Adjuster

Basin viewed from below

Rod
Adjuster

Basin viewed from below

 Adjustments to the screw on the pop-up waste plug 

base and clamp for the rods may be necessary to ensure  

maximum lift of the waste plug. Access to the clamp may 

be gained through the aperture in the base of the white 

plastic lower cover. 

Fit the Trunking:

The hot and cold supply hoses need to be enclosed within 

the white self adhesive trunking supplied.

Using the handset, raise the assembly to its highest 

position.

Remove the capping from the front of the trunking.

Remove the protective film from the self adhesive tape 

fitted to the rear of the trunking.

Pass the trunking behind the hot and cold supply hoses 

taking care to ensure that the self adhesive tape is kept 

away from the wall at this time. The top of the trunking 

needs to be aligned with the recess in the bottom left hand 

side of the rise and fall unit; through which were passed the 

supply hoses earlier.

Using a level, ensure the trunking is vertical. Once aligned, 

press the self adhesive tape against the wall to secure the 

top of the trunking. Then press the entire length of the 

trunking into position.

Fit the capping. 

 

Fit the mirror:

Remove the two white plastic caps from above the top mirror clips and remove the screws.

Place the bottom edge of the mirror into the lower catches and hold in a vertical position. Ensure 

the mirror is fitted centrally. Gently push the uppermost catches downwards into position such 

that they retain the mirror in its correct position. 

Fit the 2 security scews .

Test the unit:

Operate the handset to raise and lower the basin over the full range of travel to ensure there 

is clearance between all moving surfaces. Examine for evidence of leaks correct as necessary, 

examine and clean the assembly.

Complete  the warranty documentation and pass the completed warranty document to the client.

Содержание ABW6

Страница 1: ...Warranty No Height Adjustable Basin ABW6 OWNERS MANUAL INSTALLATION GUIDE ...

Страница 2: ...ould be facing forward towards the user when off To operate them rotate the levers outwards to achieve the flow rate required To stop water flowing rotate the levers until they are facing forward once again Operating the touch tap system The taps are usually set as wave ON Wave OFF To turn the water ON OFF pass your hand above the Sensor on the basin top Touch Tap Sensors in position ...

Страница 3: ... unit Examine the mains fuses circuit breakers and reset as necessary and ensure that mains voltage is fully reconnected then press the reset button situated next to the handset connector If the LED fails to illuminate an electrician needs to ensure that mains electrical supply is available at the fused spur a fuse may have blown elsewhere in the circuit Fault The rise and fall unit travels upward...

Страница 4: ...ble waste assembly including waste plug 1 x three hole mixer tap system 2 x 95mm long 15mm copper pipe 2 x 45mm long 15mm copper pipe 2 x compression elbow 15mm 2 x 15mm straight couplings 2 x 1 2 x 15mm Tap adaptors 2 x lever tap handles 2 x long braided hoses 2 x fibre washers 2 x screen filter seals 1 x 470mm lipped attachment rail 1 x grey 2 button handset 6 x white plastic rivets 1 x mirror 1...

Страница 5: ...equired with flush mounted a flex outlet cover on the wall behind the unit at a height of 1100mm from the floor on the centreline of the unit Fixing The basin assembly should be fixed to a load bearing wall i e strong enough to carry a 100kg load on wall fixing which is flat and free from obstruction from 200mm 2200mm above the floor If the basin needs to be fixed to a stud wall the wall will need specia...

Страница 6: ...ith the one on the wall Ensure that the unit is level then mark the wall through the remaining three attachment points two on the lower horizontal beam and one on the upper horizontal beam Remove the unit from the wall and at the three marked positions drill three 6mm full depth pilot holes Open the two to accept Anchor fixings Open the upper hole to 10mm to accept a plastic wall plug Fit the fixi...

Страница 7: ...ke sure the rod can move freely Using the adjusting screw set the overall length of the basin plug to 77mm Stand the lower cover in place Fit the plug lifting rods in position and set the clamp to lift the plug Touch taps Fit the sensors before mounting the unit on the wall Touch tap sensors should be fitted in the position agreed with the client Drill an 18mm in the position required take care to...

Страница 8: ... brass nut Test the water supply Ensure the isolation valves are CLOSED Place a bucket or suitable container below the plug hole of the basin Open both basin taps fully and then slowly open each of the isolation valves wait 2 minutes then examine the supply system for leaks correct as necessary Close the isolation valves Fit the white plastic lower cover Remove the mushroom heads from the plastic ...

Страница 9: ... supply hoses need to be enclosed within the white self adhesive trunking supplied Using the handset raise the assembly to its highest position Remove the capping from the front of the trunking Remove the protective film from the self adhesive tape fitted to the rear of the trunking Pass the trunking behind the hot and cold supply hoses taking care to ensure that the self adhesive tape is kept awa...

Страница 10: ...Page 10 Version 3 01 04 2016 ...

Страница 11: ...Page 11 Version 3 01 04 2016 ...

Страница 12: ...821110 Technical Helpline 01242 822972 2013 Astor Bannerman Medical Limited Our policy is one of continuous development and we therefore reserve the right to make technical alterations without notice The content of this publication may not be copied either whole or in part without the consent of Astor Bannerman Medical Limited Original Document ...

Отзывы: