INSTALLATION
(continued)
1--4
Press until light
FLASHES
Press for 15 Seconds
Florham Park NJ 07932 USA
TRANSFER SWITCH TEST
BYPASS TIME DELAY
SET ENGINE EXERCISER
observe these lights
Figure 1–5. Standard controls and indicators.
2 – Voltage Checks
First check nameplate on transfer switch; rated voltage
must be the same as normal and emergency line voltages.
Verify that the feeders have been
connected to the proper lugs.
!
Use extreme caution when using a meter
to measure voltages in the following
steps. Do not touch power terminals;
shock, burns, or death could result !
Perform steps 1 through 6 at the right. Observe the status
lights. See Figure 1–5.
●
Black circle means light is on.
❍
White circle means light is off.
* If necessary, adjust voltage regulator on the generator
according to the manufacturer’s recommendations. The
Automatic Transfer Switch will respond only to the rated
voltage specified on the Transfer Switch nameplate.
1
Close the normal source circuit
breaker. The
Transfer Switch
Connected To Normal
and the
Normal Source Available
lights
should come on.
2
Use an accurate voltmeter to
check phase to phase and
phase to neutral voltages pres-
ent at the transfer switch normal
source terminals.
3
Close the emergency source
circuit breaker. (Start generator,
if necessary.) The
Transfer
Switch Connected To Normal
and the
Emergency Source
Available
lights should come on.
4
Use an accurate voltmeter to
check phase to phase and
phase to neutral voltages pres-
ent at the transfer switch emer-
gency source terminals.*
5
Use a phase rotation meter to
check phase rotation of emer-
gency source; it must be the
same as the normal source.
A B C
6
Shut down the engine–genera-
tor, if applicable. The
Emergen-
cy Source Accepted
light should
go off. Then put the starting
control selector switch (on the
generator set) in the
automatic
position. Close enclosure door.
Now continue to
3 – Electrical Operation
on next page.