Pitched roof mount installation manual – Version 2016 1.0 to AS/NZS1170.2.2011 Amdt 3
–
2012 13
12. Place the last module in the row on the rails (with
the first row of modules, take care that the nti-slip
protection sits properly in the rail channel) and fasten
the last inter module clamp and the module end clamp
using the Allen Key (recommended torque is 8 Nm).
13. For each use of the T module. You must make sure
that: the thread of the screws does not project through
the lower side of the T module (max flush). Position
the T module in the rail channel and fasten it loosely
with2 to 3 turns of the screw. The screws can still be
freely moved in the rail channel. Slide the screw to
their final position in connection with the inter-module
clamp, module end clamp or roof hooks/hanger bolts
and fastens firmly.
14. Now first row of modules are installed, continue to
mounting next row of modules according to steps 7 to
10.
15.Antai rail grounding system