AIR PURGING METHOD IS PROHIBITED FOR R32 SYSTEM 

11.4  Air Tightness Test on the Refrigerating System 

Before system charged with refrigerant and before the refrigerating system in put into operation, below site test 
procedure and acceptance criteria shall be verified by the certified technicians, and/or the installer:- 
 
Step 1: Pressure test for refrigerant leak detection: 
1)  Steps for pressure test, in accordance to ISO 5149. 
2)  Evacuate the system from refrigerant before the leak test, attach the gauge manifold set correctly and tightly. 

Charging hose of Low side connect to Gas side. (Charging hose of High side connect to Liquid side if applicable.) 

3)  Adjust the knob on the service valves, and regulator on the gauge set, so that test gas can be inserted through 

the centre manifold of the gauge set. 

4)  Insert Nitrogen gas into the system through the centre manifold and wait until the pressure within the system to 

reach about 1 MPa (10 BarG) wait for a few hours and monitor the pressure reading on the gauges. 

5)  Please note that the system’s pressure may rise slightly if the test is carried out on mid day, due to temperature 

rise. The inverse may happen when there is temperature drop at night. However, this variation will be minimal. 

6)  Waiting time depends on the size of the system. Larger systems may require 12 hours of waiting time. Leak 

detection within smaller system can be achieved in 4 hours. 

7)  Check if there is a constant pressure drop. Move to next step “Step 2: Refrigerant leak detection…” if there is any 

pressure drop. Otherwise, release the Nitrogen gas and, move to “Step 3: Evacuation of the equipment”. 

8)  Next, insert a small amount of same refrigerant into the system through the centre hose, until the pressure 

reaches about 1 MPa (10BarG). 

 

7

N

2

R - ###

2

2

(Low/Gas) pressure gauge

(High/Liquid) pressure gauge

An example illustrations of setup
for refrigerant leak detection.

3

4

8

 

 

Step 2: Refrigerant leak detection through Electronic halogen leak detector and/or ultrasonic leak detector: 
1)  Use any one of below detector to check leaking. 

i. 

Electronic halogen leak detector. 
i-a) Switch on the unit. 
i-b) Cover the test area from direct draft. 
i-c) Pass the detection probe near test area and wait for audible and visible signals. 

ii. 

Ultrasonic Leak Detector. 
ii-a) Make sure the area is quiet. 
ii-b) Switch on the ultrasonic leak detector. 
ii-c) Move the probe along your air conditioning system to test for leaks, and mark for repair. 

2)  Any leak detected at this level shall be repaired and retested, starting from “Step 1: Pressure test”. 
 
NOTE: 

Always recover the refrigerant and Nitrogen gas into recovery cylinder after completion of a test. 

You must use the detection equipment with Detectable Leak Rate of 10

-6

 Pa. m

3

/s or better. 

Do not use refrigerant as test medium for system with total refrigerant charge more than 5 kg. 

Test shall be performed with dry Nitrogen or another non-flammable, non-reactive, dried gas. Oxygen, air or 
mixtures containing them shall not be used. 

 
 
 

AMP Air Conditioning

www.ampair.co.uk | [email protected]

Содержание CU-4Z80 Series

Страница 1: ...iping Amin M 2 5 LFL 5 4 h0 2 Amin Required minimum room area in m2 M Required charge amount in appliance in kg LFL Lower flammable limit 0 306 kg m3 h0 Installation height of the appliance 1 8 m for...

Страница 2: ...Unit Installation Diagram 1 Fix the unit on concrete or rigid frame firmly and horizontally by bolt nut 10 mm 2 When installing at roof please consider strong wind and earthquake Please fasten the ins...

Страница 3: ...side of CS MZ16 CS TZ25 CS MTZ16 CS TZ35 CS Z20 CS TZ42 CS Z25 CS TZ50 CS Z35 CS TE20 CS Z42 CS TE25 CS Z50 CS TE35 CS XZ20 CS TE42 CS XZ25 CS TE50 CS XZ35 CS E9 CS XZ50 CS E12 CS TZ20 CS E18 Liquid s...

Страница 4: ...if there is a constant pressure drop Move to next step Step 2 Refrigerant leak detection if there is any pressure drop Otherwise release the Nitrogen gas and move to Step 3 Evacuation of the equipmen...

Страница 5: ...ptor Outdoor unit Liquid side Gas side OPEN Vacuum pump Liquid side 3 way valve Gas side 3 way valve Liquid side Gas side Tube connector Tube connector Tube connector Tube connector Close Close Indoor...

Страница 6: ...s at the interface point are sufficient for the installation of the equipment CU 4Z80 Unit D Unit C Unit A Unit B Indoor Outdoor connection cable Power Supply Cord Isolating Devices Indoor Unit A Indo...

Страница 7: ...remove the burrs 2 Remove the burrs by using reamer If burrs is not removed gas leakage may be caused Turn the piping end down to avoid the metal powder entering the pipe 3 Please make flare after in...

Отзывы: