background image

     www.amico.com     

11

NuLook FlexWall - Engine

TOP

TOP

TOP

TOP

TOP

TOP

Gas ports

OXY

VAC

AIR

TOP

VAC

V A O

L

C

BLOCKING

BLOCKING

NO FLY ZONE

maximum ceiling height  :108"

Panel starts 8"-10" AFF.

LV

TERM BOX

HIGH POWER TERM BOX

HIGH POWER TERM BOX

minimum unit height  :90"

1

2

3

4

6

8

9

11

5

7

10

Horizontal opening required to install 

stud frame is 

52 1/8"

2" [51 mm Termination Box from 

Top of Stud TYP.

81 5/8" [2,073 mm]

Maximum Ceiling Height: 108"

Minimum Unit Height: 90"

Panel starts at 8"-10" AFF

Blocking (provided by others)

Blocking (provided by others)

4 3/4" [120 mm]

77 3/4" [1,975 mm]

12

2" [

3,

09

9 m

m

] [

St

ud H

ei

gh

t + 2

" m

in

.]

64" [1,626 mm]

33 5/8" [855 mm]

19 5/8" [499 mm]

View A-A

NO FLY ZONE

Содержание NuLook FlexWall

Страница 1: ...Installation lnstructions NuLook FlexWall...

Страница 2: ...are should be taken to prevent injuries and damage NOTE Steps that point out helpful information IMPORTANT Be sure to observe this instruction 1 Review a copy of the final approved shop drawing s and...

Страница 3: ...e 1 Hardware 2 8 Self Drilling Flat Head Screw Yellow Zinc Plated Part H SDF QX 08125 1 1 4 X 8 X 8 X 8 X 6 0 164 Head Cap Screws 1 4 x 3 4 Part C H HDCAP 0207 1 4 BS Plate Washer Part C H WFS 02 1 4...

Страница 4: ...fore fastening The Amico Engine NOTE Please refer to the dimensions indicated on shop drawings 2 Insert Engine into tracks using lift and drop method Figure 1 Installation Figure 1 Engine Installation...

Страница 5: ...TE Medical gas pipes and electrical are terminated as per shop drawing WARNING Only for Back to back units with 3 5 8 studs braze the gas pipes with caution to prevent any damage to the acoustic sheet...

Страница 6: ...ANT See Page 10 for panel removal and handling instructions Step 2 Drywall Installation Provided by Others IMPORTANT Before installing drywall make sure the blocking is provided on the exact location...

Страница 7: ...middle unit 5 Align the sections and connect in 4 places along the vertical edges of each section Figure 5 using the hardware provided as shown in Hardware 1 IMPORTANT Make sure the frames are flush a...

Страница 8: ...4 screws 7 Connect the medical gases to the FlexWall Engine NOTE The ends of Hose Assemblies have gas specific adapters meant to plug into the FlexWall Engine WARNING Orient and secure gas hoses so th...

Страница 9: ...its to the termination box and install cover plates over the box 10 Attach all removed items Panels must clip in properly where applicable Devices and cover plates Reinstall the rails if applicable IM...

Страница 10: ...s where applicable Remove Top Plate Remove Insert Strip Remove Screws 2 Remove device cover plates and gases 3 Remove panels using the provided suction cup WARNING Stack panels face to face to prevent...

Страница 11: ...ERM BOX minimum unit height 90 1 2 3 4 6 8 9 11 5 7 10 Horizontal opening required to install stud frame is 52 1 8 2 51 mm Termination Box from Top of Stud TYP 81 5 8 2 073 mm Maximum Ceiling Height 1...

Страница 12: ...oration 85 Fulton Way Richmond Hill ON L4B 2N4 Canada 600 Prime Place Hauppauge NY 11788 USA Toll Free Tel 1 877 462 6426 Tel 905 764 0800 Fax 905 764 0862 Email info amico com www amico com ACA IM NU...

Отзывы: