2
MAKE WATER SUPPLY CONNECTIONS
4
TEST INSTALLED FAUCET
3
INSTALL WEIGHTS
Move HANDLE (1) down into
"off" position.
With HANDLE (1) down in "off" position,
unthread SPRAY FACE (3) from SPRAY (2).
Turn on water supplies.
Operate handle up and down, in COLD
and HOT positions, to flush water lines
thoroughly.
Check HAND SPRAY (2) operation:
Switch between two functions using SWITCH (3).
Replace SPRAY FACE (3) onto SPRAY (2).
With HAND SPRAY (1) seated in FAUCET (2),
install WEIGHT (4) onto HOSE (3) using the
LATCH (5). Locate the WEIGHT (4) two feet (2')
from the underside of the sink deck.
Check connections for leaks.
(See Section 5)
3
2
2
1
2
COLD
HOT
Turn off hot and cold water supplies before beginning.
Connect FLEXIBLE SUPPLIES (1, 2) directly
to wall supplies. Connection on fitting
supplies are 3/8" compression. Connect
left supply (Marked with a Red Stripe) to Hot
and right supply (Marked with Blue Stripe) to
Cold wall supply. Use adjustable wrench to
tighten connections. Do not over tighten.
Faucet supplies are 21" long from faucet base.
Note: If additional supply length is
required, installer must purchase
additional parts separately.
Important: If SUPPLY HOSES (1, 2) are
too long, loop as illustrated to avoid kinking.
3
1
2
24"
3
REMOVE
M965774 Rev. 1.2 (4/21)
5
4
1