EDM Installation and Maintenance Instructions
Anchoring the Turnstile
Anchoring Holes
(2 total)
Concrete Anchor
(Head and arms not shown for ease of view)
Access
Panels
Anchor
Locations
Fig. 4
Fig. 5
Fig. 6
Use included Shim Kit as
necessary to level turnstile and
prevent rocking.
NOTE
1. Using a turnstile leg key, open the turnstile leg
access panels [Fig. 4].
2. Using a 9/16" socket wrench, remove the four (4)
bolts that secure the temporary wood plate to the
turnstile. Discard the wood plate.
3. Place the turnstile in the desired location.
For fixed installations, primary power terminal block
and power button are always located on the secured
or internal side of the facility. Keep this in mind
when placing primary power conduit and turnstiles
according to the project layout.
4.
Transfer four (4) anchor locations to the floor [Fig. 5].
5. Move the turnstile to the side.
6.
Using a hammer drill fitted with a 5/8” concrete bit,
drill each anchor hole to a depth of 3” (76.2mm).
7. Using a shop vac, vacuum debris from the anchor
holes before installing the anchors. If the holes are
not clear of debris, the anchors may not tighten
properly.
8. Insert anchors into the drilled holes with the threaded
ends down. If needed, use a hammer to tap the
anchors into place. Ensure that the anchors are flush
with the concrete floor [Fig. 6].
9. Return the turnstile to the install location, ensuring
the anchors holes are aligned.
10. Insert anchor bolts.
11.
Using a torque wrench (ft-lbs.) and 9/16” socket,
torque the bolts to 20 ft.-lbs.
12. Route primary power and access control wiring
through the appropriate conduit opening into
the turnstile [Fig.5]. Primary power wiring will be
connected in later steps.
13. For outdoor installations, apply a thick bead of clear
RTV silicone around the base of turnstile legs to seal.
NOTE
Conduit Openings