MST Installation Instructions

Installation Instructions                [email protected]   +1(909) 591-8431    www.alvaradomfg.com

 

 

Page 7

Turnstile 

 

Center

Installation Instructions

NOTE

 

Install the turnstile on a 6' x 6' (min.) level concrete slab. The slab must 

be a minimum of 4" thickness. The turnstile may only be installed on 

concrete. Do not install the turnstile on asphalt.
DIMENSIONS SHOWN ARE FOR MST-3 and MST-6X MODELS. SEE 

APPENDIX A-D FOR OTHER MODELS.

NOTE

 

The turnstile is rated for both indoor and outdoor use. 

Installation Locations

1. 

Determine where the turnstile will be installed.  

 

Consider the overall footprint size of the unit when  

 

determining the  installation location (Figure 1).  

 

Once the installation location has been determined,  

 

use a chalk line to mark  the centerline of the  

 turnstile.

 

NOTES

 

Default entry rotation is counterclockwise.  

Confirm correct entry direction prior to 

 

installation.
Alvarado recommends that the minimum  

installation width required be 64".

62.00" 

(1575mm)

54.00" 

(1372mm)

2. 

Determine and mark the centerline location for the  

 

OV, Roto, and Yoke (Figure 2).

 

NOTE

 

The overall height of the MST is 91.5". However, an 

additional 3" of clearance must be added for service 

and maintenance.
If desired, installers can stub up the power conduit at 

the intersection of the turnstile centerline and the OV 

centerline. Power may also be routed directly into the 

top channel (Figure 26).
Mark all center lines prior to installation.

Fig. 1

Fig. 2

Roto Centerline

29.63" 

(752mm)

30.0" 

(762mm)

CL

CL

O

N

Yoke Centerline

Entry Side 

 (Unsecured)

Exit Side  

(Secured)

31.5" 

(800mm)

30.5" 

(775mm)

OV Centerline

30.0" 

(762mm)

29.63" 

(752mm)

Содержание CLST-3

Страница 1: ...ration Instructions Alvarado Manufacturing Company Inc 12660 Colony Street Chino CA 91710 Phone 909 591 8431 Fax 909 628 1403 support alvaradomfg com www alvaradomfg com FULL HEIGHT MAXIMUM SECURITY T...

Страница 2: ...nduit Instructions 16 Electrical Wiring Instructions 17 Turnstile Control Board Layout 18 Terminal Descriptions 19 SW4 DIP Switch Descriptions 21 User Activation and Passage Instructions 22 Post Insta...

Страница 3: ...skilled individuals maintain the turnstile according to a proper maintenance schedule In access control applications train all personnel that will be using the turnstile in the proper method of opera...

Страница 4: ...NG For continued protection against risk of fire or shock replace with the same type and rating fuse c UL 294 Access Control Levels Destructive Attack Level 1 Line Security Level 1 Endurance Level 4 S...

Страница 5: ...Qty 1 10 32 x Allen Head Screw Qty 6 x 1 Hex Head Bolt Qty 1 x 1 Hex Head Bolt Qty 2 x 2 Hex Bolt Head Qty 2 10 x Phillips Pan Head Screw Qty 10 Nut Qty 5 x 2 Anchor Bolt Qty 12 Flat Washers Qty 12 x...

Страница 6: ...e with key locks located on the underside of the top channel to allow key override control of the roto Separate key overrides are provided for each rotation direction For manual units 3 models the key...

Страница 7: ...location has been determined use a chalk line to mark the centerline of the turnstile NOTES Default entry rotation is counterclockwise Confirm correct entry direction prior to installation Alvarado re...

Страница 8: ...4 Insert one anchor into each drilled hole Figure 4 The threaded end of the anchor must be inserted into the hole first Use a hammer to tap the anchor into place if needed Ensure that the anchors are...

Страница 9: ...r hole and anchor it with one x 4 anchor bolt and flat washer NOTE Prior to drilling the remaining anchor holes use a tape measure and measure the distance from the bottom bearing plate center to the...

Страница 10: ...must be inserted into the hole first Use a hammer to tap the anchor into place if needed Ensure that the anchors are flush with the concrete floor 5 Place the OV back over the anchor holes and anchor...

Страница 11: ...cess grease 3 When complete refer to Figure 17 for correct orientation Top Channel Installation A minimum of two people is required to complete the installation of top channel 1 Remove the cover from...

Страница 12: ...aught between the top channel and the yoke roto or OV as this may damage the wires 4 Align the top channel spline shaft with the roto cavity and carefully lower the top channel spline shaft into the r...

Страница 13: ...head bolts from the underside of the top channel up through the mounting holes and secure with two lock washers and two nuts Figure 21 8 Hand tighten the top channel mounting hardware at this time usi...

Страница 14: ...g screws Figure 23 Mounting Screw Bearing Cover Installation Top Bearing Cover Installation Bottom Bearing Cover Installation 1 Place the two halves of the bottom bearing cover over the bottom bearing...

Страница 15: ...Fig 25 Drill 64 9 Drill Bit 10 x Phillips pan head screw Screwdriver NOTE Be sure the guard plate and the yoke are aligned properly and flush before performing the following step s Be sure that the tu...

Страница 16: ...ion Run conduit to the top channel cover in one of the locations shown in Figure 27B Punch conduit hole at least 2 5 from the bottom of the top channel lid Conduit must be run all the way to the junct...

Страница 17: ...for 110V 220V configuration 7 Tuck the excess wire into the junction box and re attach the junction box cover 8 Once power has been established route the access control wires NOTE If your model was p...

Страница 18: ...AUX Fire Alarm Input N O Clockwise Fail Safe Counterclockwise Fail Safe Timer See Chart to the Right Timer See Chart to the Right Feedback Pulse 300ms JS2 LED Option 1st Sensor Optics AUX Fire Alarm I...

Страница 19: ...inuous dry contact at this terminal places the turnstile in a locked CLOSED mode This mode overrides the access control system operation If status lights are installed Location J19 the red light will...

Страница 20: ...TC uses input from the sensors to monitor rotation of the Roto J11 CNT RESET Connection for counter reset key switch 1 06VDC 5 A N O contact connection if counter wires are attached to J2 and or J8 co...

Страница 21: ...ease lock arm for rotation Adjusts automatic re lock timing See Figure 28A for settings T3 T3ON Adjusts automatic re lock timing See Figure 28A for settings Adjusts automatic re lock timing See Figure...

Страница 22: ...the turnstile Figure 31 Keeping your arms extended gently push on roto arm section A and slowly walk through the turnstile Figure 31 Stay near the yoke and take short steps Once you have traveled thr...

Страница 23: ...rado recommended commercial products see Cleaning and Maintenance Section Stainless Steel units with optional coating wipe down entire turnstile with clean water Hot Dipped Galvanized wipe down the st...

Страница 24: ...tion FAIL SAFE FAIL LOCK CONFIGURATION Fail Safe Direction A B C D E F G H I J K L M N O L K J I H F E C D B O O N N M M P P NOTES The steps contained in this Troubleshooting section are the most comm...

Страница 25: ...s listed above did not solve the issue contact Technical Support Power Issues Cause Solution Reference Green LED is OFF 1 Verify that the power switch is in the ON position and that primary power is p...

Страница 26: ...nsors for a correct reading Fig 28 D F Fig 32 M Fig 32 M N Optical sensors are bad If the steps above did not resolve the problem the issue most likely lies with the optical sensors Please contact Tec...

Страница 27: ...the OPN signal is connected to the access control system verify that the OPN signal is not being provided with a continuous dry contact B Press SW7 and swipe a business card counterclockwise through...

Страница 28: ...effort NOTE If the distance is exceeded self centering may not operate correctly Issue Solution Reference Customer would like the turnstile to rotate with less pushing force The pushing force require...

Страница 29: ...ed Rinse the surface after cleaning Damaged galvanized areas can be treated or touched up with zinc rich paint Use an organic cold galvanizing compound following the manufacturer s instructions An exp...

Страница 30: ...tainless steel Alvarado recommends the use of a citric acid product CitriSurf2310 available from Stellar Solutions www citrisurf com This product is especially formulated to clean and passivate stainl...

Страница 31: ...m Lubricant lubricant with a tube extension applicator NOTE Use only Alvarado springs and only the springs designated for the location and use purpose Turnstile springs are not interchangeable and sho...

Страница 32: ...he turnstile 4 to 5 times to ensure the lubricant is spread evenly along the slide rods Fig 37 Lower Shaft Bearing Main Cam and Lower Shaft Bearing Figure 37 Lubricate the grease fitting on the lower...

Страница 33: ...irection prior to installation Yoke Qty 1 Roto Qty 1 OV Qty 1 CPST Illustrated Parts List Yoke Mounting Channel Qty 4 Channel Mounting Screws Qty 8 These instructions are for installing the yoke secti...

Страница 34: ...ns Figure A1 Adjust the yoke until these two distances are identical Mark these two locations 3 Use a pencil and trace the entire outline of the yoke assembly Figure A3 4 Locate the four 4 yoke mounti...

Страница 35: ...ocket Wrench x 2 HHCS Bolt and Flat Washer Mounting Channel Mounting Channel Yoke Assembly Mounting Channel 20 x 1 screw Fig A8 Yoke Installation Cont Fig A6 Fig A8 A6A 6 Using a concrete drill bit dr...

Страница 36: ...n Appendix A Figures A2 A8 When complete refer to the OV Installation to continue the installation Yoke Qty 1 Roto Qty 1 OV Qty 1 CLST Illustrated Parts List Fig B1 Yoke Mounting Channel Qty 4 Channel...

Страница 37: ...ntry direction prior to installation 2 Reconfirm the centerline location for the yoke Figure C2 3 Continue installation as shown in the Yoke Installation section Fig C1 Fig C2 Bottom Bearing Plate Cen...

Страница 38: ...ver an additional 3 of clearance must be added for service and maintenance 2 Reconfirm the centerline location for the Yoke Figure D2 3 Continue installation as shown in the Yoke Installation section...

Страница 39: ...CW Lock Arm Fail safe Solenoid B Black Red Fail lock Solenoid CW Lock Arm A Return Spring B Solenoid Spring A B Black Silver 1 Spring Configuration 2 Solenoid Mount Position NOTES Spring Solenoid Oper...

Страница 40: ...unting positions 1 2 A Return Spring B Solenoid Spring CCW Lock Arm Fail safe Solenoid A B Fail lock Solenoid B A A Return Spring B Solenoid Spring Black Red Black Silver CCW Lock Arm 1 Spring Configu...

Страница 41: ...g positions 2 1 Spring Configuration 2 Solenoid Mount Position A Return Spring B Solenoid Spring CW Lock Arm Fail safe Solenoid A B Black Red Fail lock Solenoid CW Lock Arm A Return Spring B Solenoid...

Страница 42: ...g positions Increase spring tension Decrease spring tension Increase spring tension Decrease spring tension A Return Spring B Solenoid Spring CCW Lock Arm Fail safe Solenoid A B Fail lock Solenoid B A...

Страница 43: ...on Figure 3 2 Slide cam to engage the lock arm tab securely and completely tighten the mounting screw Cam Cam Shaft Lobe Setup CW Lock Arm Override Fig 3 NOTE If key cannot be removed or lock arm does...

Страница 44: ...d CCW lock arm open and rotate the key to the override position Figure 3 2 Slide cam to engage the lock arm tab securely and completely tighten the mounting screw Setup Cam Cam Shaft Lobe CCW Lock Arm...

Страница 45: ...connection to turnstile control board section 6 1 11 6 2015 A Flores SW4 DIP switch 8 configures OPN inputs as either normally open N O or normally closed N C Replaced Tri Flow Lubricant with DuPont...

Страница 46: ...10 Toll Free 800 423 4143 Fax 909 628 1403 information alvaradomfg com www alvaradomfg com 2014 Alvarado Manufacturing Company Inc This work may not be reproduced published or redistributed in whole o...

Отзывы:

Похожие инструкции для CLST-3