Alpha ESS Co., Ltd.
Page 19 of 46
Your Smart Energy
Installation
Step 8: Install ethernet communication cable, as shown inFigure 2.13. It won‘t be needed if using
WiFi module.
Note: The ethernet communication cable can be connected wiring directly through
the silica gel ring of the M20 waterproof contact, no need to make the on-site network
cable. The maximum outer diameter of the network cable does not exceed 14mm.
Figure 2.14 Install WiFi Module
Note: If using WiFi module, open the cover plate of the side WiFi module, insert the
WiFi module into the terminal port and then fix it with screws, as shown in Figure 2.14.
If you will install extrenal M4856-P for expansion, please goto section 2.4.4 directly.
Step 9: before re-covering the upper cover plate, please turn on the internal 63A switch.
Figure 2.15 Re-cover the Upper Cover Plate
Step 10: the wiring is completed, please connect the wiring harness on the back of the upper
cover plate. Then re-cover the B3 upper cover plate, use the M5 internal hexagonal wrench to
tightly lock the upper cover screw, and then install the white plug, as shown in Figure 2.15.
Note: the upper wiring harness from EMS shall be connected to the back upper part ,
the below wiring harness from BMS shall be connected to the back below part. Please pay
attention to the positive and negative pole of the button switch wires.
The suggested torque is 2.6 N.m±10%. For capacity expansion, please refer to the
accessory package attached for details.