[AKD4396-SBW]
<KM078103> 2 2011/03
Operation sequence
1) Set up the power supply lines. (See “Other jumpers set-up”.)
Name Color Voltage
Comments
Attention
+15V Red
+12
∼
+15V
Regulator,
Power supply for Op-amp.
This jack is always needed. Power line
-15V Blue
-12
∼
-15V
Regulator,
Power supply for Op-amp.
This jack is always needed. Power line
AGND
Black
0V
GND
This jack is always needed.
Table 1 Set up of power supply lines
Each supply line should be distributed from the power supply unit.
2) Set-up the jumper pins
3) Set-up the DIP switches. (See the followings.)
4) Power on
The AK4396 should be reset once bringing SW1 (PDN) “L” upon power-up.