TF7038GB_A_NOT
3.
RECEIVING AND MOVING THE UNIT
The unit is shipped ex works wrapped in foil. Before moving the unit, the load capacity of the hoists used
must be checked. The unit may only be moved by qualified and suitably equipped personnel.
HANDLING THE UNIT:
If belt lifting is to be used, place protective parts between the belt and the housing to prevent damage to
the structure. All coverings must be firmly secured before handling the unit. Before lifting, the specific
weight must be checked on the technical type plate. Use all specified lifting points and only these points.
Use ropes of the same length in accordance with the regulations. Use a spacer that complies with the
regulations (not included). Handle the unit carefully and without jerking.
CHOOSING THE INSTALLATION SITE
The units are subjected to a final inspection at the factory and only need to be connected to the
electricity and water supply at the installation site.
Before the unit is installed, its installation location must be agreed with the customer, and the following
points must be observed:
The supporting surface must be able to withstand the weight of the unit.
The safety distances between the units and other devices or building elements must be strictly
observed.
The device must be installed by a technician in accordance with the applicable national laws of
the country of use.
The technically required minimum clearances must be provided in order to allow work to be carried
out for REGULAR AND EXTRAORDINARY MAINTENANCE.
It should be noted that the refrigeration unit may transmit vibrations during operation; it is
therefore recommended that the vibration damping brackets are attached to the base in
accordance with the installation diagram.
When securing the unit, check carefully that it is balanced.
14