Modules must be securely attached to the mounting 
structure. For clamping system installation, the 
recommended maximum compression for each clamp is 
2900 PSI (20 Mpa) in order to avoid potential damages 
to module frames; follow the instructions provided by 
the clamping system supplier. 

!

Avoid exposing the frame to lateral tension and 
pressure, as this might crush the glass or spark 
a fire. Consider the linear thermal expansion of 

the frames: the recommended minimum distance 
between two modules is 1 cm.

For ground-mounted systems, the minimum distance 
recommended from the ground to the module bottom 
is at least 60cm (24 inches).  
 
For roof-mounted systems, always ensure the suitability 
of the roof construction before installing the modules 
on a roof. In addition, any point of roof penetration 
required to mount the modules must be properly 
sealed to prevent leaks.

Provide adequate ventilation under the modules in 
conformity to local regulations. A minimum distance 
of 10 cm between the roof plane and the frame of 
the module is generally recommended. Never allow 
modules to overlap or to exceed the rooftop size.

When installing a module on a pole, select a pole and 
module mounting structure that will withstand the 
anticipated wind load and snow load for the area.

AEG glass-glass PV modules can be installed with: 
•  frame  mounting  holes  and  bolts  –  See  3.2.1  “Bolting”                                                                                     
•  pressure clamps – See 3.2.2 “Clamping”

3.2.1 Bolting

Always observe the instructions and safety precautions 
of the mounting system. Modules must be securely 
fixed to the mounting system (support rails) using the 
provided mounting holes. There are 4 (four) mounting 
holes placed to optimize the load handling capability of 
the module and to secure it to the supporting structure. 
If increased wind or snow-loads are expected, the 
additional mounting holes provided should be used.
It is recommended to use corrosion proof (stainless
steel) hardware. Stainless steel M8 bolts and a 
tightening torque of 15-20 N 

• 

m are suggested. Please 

check with your system designer or installer the specific 
load calculations for your plant and refer to figure 3 and 

figure 5 for details.

Figure 3: Bolting

3.2.2 Clamping

Installation using pressure clamps can be done on both 
sides of the module frame. Use at least 4 (four) clamps 
per module, two on each long side of the module (for 
portrait orientation) or two on each short side of the 
module (for landscape orientation). Depending on the 
local wind and snow situation, additional clamps might 
be required to ensure the module is able to withstand 
the load. Module clamps should not come into contact 
with the front glass and should not deform the frame. 
Ensure to avoid shadowing from module clamps. Please 
refer to figure 4 and figure 6 for details. 

Figure 4: Clamping

Bolt

Flat washer

PV module

Frame

Mounting rails

Clamp A

Flat washer

Spring washer

Nut

PV module

Frame

Mounting 

 rails

Clamp B

Flat washer

Spring washer

Nut

Flat washer

Bolt

Bolt

Flat washer

PV module

Flat washer

Spring washer

Nut

Содержание AS-M2-G Series

Страница 1: ...AEG GLASS GLASS MODULE INSTALLATION MANUAL GD202008 V1 20 VERSION AEG SOLAR MODULES INSTALLATION MANUAL GLASS GLASS DOUBLE GLASS MODULE SERIES AS MXXX2 G ...

Страница 2: ...portant information for product care maintenance and disposal CONTENTS 1 1 Icons 2 1 2 Product Identification 2 2 Safety 3 2 1 General safety 3 2 2 Handling safety 3 2 3 Installation safety 3 2 4 Fire safety 4 3 Installation 4 3 1 General remarks 4 3 2 Mechanical installation 5 3 2 1 Bolting 5 3 2 2 Clamping 6 3 2 3 Loading capacity 6 3 3 Electrical Installation and Grounding 7 3 3 1 General remar...

Страница 3: ...ure 2 Example of product technical drawing Please refer to the specific product datasheet on www aeg industrialsolar de for the latest technical data 2 SAFETY 2 1 General safety All AEG PV modules should be installed according to all local and national applicable standards codes and regulations Only qualified personnel should install the solar modules Installers bear the risk of all injury that mi...

Страница 4: ...er metallic devices while installing or troubleshooting photovoltaic systems in order to avoid electric shock Do not disconnect modules under load to avoid electrical arcs Contact with electrically active parts of the modules such as terminals can result in burns sparks and lethal shock whether or not the module is connected Do not insert electrically conductive parts into the plugs and sockets Do...

Страница 5: ...ce of the modules to sea water or lakes should therefore be at least 500 mt unless otherwise specified The module should not be exposed to unusual chemical loads For fire safety indications please see 2 4 Fire safety Protect the solar modules from overvoltage e g voltage peaks of battery charges generators etc If the module has to be connected to a storage battery all precautions as prescribed by ...

Страница 6: ...lting pressure clamps See 3 2 2 Clamping 3 2 1 Bolting Always observe the instructions and safety precautions of the mounting system Modules must be securely fixed to the mounting system support rails using the provided mounting holes There are 4 four mounting holes placed to optimize the load handling capability of the module and to secure it to the supporting structure If increased wind or snow ...

Страница 7: ... Pa Allowed assembly with clamp 0 H 1 4W Allowed assembly with clamp 0 H 1 4W Figure 6 Clamping Loading capacity scheme Mounting by insertion Load positive 1600Pa negative 1600 Pa Load positive 5400 Pa negative 2400 Pa Allowed assembly with clamp 1 2L 50 S 1 2L 50 Figure 7 Insertion Loading capacity scheme 3 3 Electrical Installation and Grounding 3 3 1 General remarks Modules electrically connect...

Страница 8: ...ironmental conditions Always ensure that the modules are assembled with the appropriate string fuse for circuit protection based on the maximum series fuse rating of the module and local electrical installation codes There is no specific limitation on the number of modules that can be connected in parallel the number of modules is determined by system design parameters such as current or power out...

Страница 9: ...ing maintenance Follow the maintenance instructions for all components used in the system such as support frames charge regulators inverters batteries etc 4 2 Cleaning Do not clean modules with broken glass or exposed wiring This can cause a general electrical failure of the module or electrical shock hazard Dirt and dust can accumulate on the glass surface of the PV module over time particularly ...

Страница 10: ...ation use and maintenance of the product are beyond Solar Solutions s control Solar Solutions expressly disclaims liability for loss damage or expense arising out of or in any way connected with such installation operation use or maintenance No responsibility is assumed by Solar Solutions GmbH for any infringement of patents or other rights of third parties which may result from use of the PV prod...

Отзывы: