Installation Manual : X-TENSION 350 Median
Ph 1800 724 172 or visit
www.acprod.com.au
December 2018
/ Page 12
Step 5 - Hang Rail 2 and Shear Bolts
Before installing rail 2
double check that the blockout is already bolted to post 3.
Bolt rail 2 to the post and blockouts at posts 4 and 5 with the appropriate post bolt (Figure 11).
DO NOT BOLT THE RAIL TO POST 3.
Splice rail 2 to rail 3 with
the 8 special shear bolts (yellow) supplied (Figure 12)
.
Put the
washer and nut on inside of rail.
IMPORTANT NOTE: DO NOT USE STANDARD SPLICE BOLTS AT POST 5 SPLICE
Figure 11. Bolt rail 2 to post and blockout
Figure 12. Splice rail 2 to rail 3 with 8 special
shear bolts
Step 6 - Attach Slider Bracket to Rail 2
Bolt the Slider Bracket to the end of rail 2 at post 3 (Figure 13). Use 4 standard splice bolts.
The angle bar end should be closest to the Impact Head end.
Remove the angle bar and 2 x
M20 x 40mm bolts (Figure 14).
Figure 13. Bolt Slider Bracket to end of rail 2
Figure 14. Remove angle bar bolts
at post 3