PROBOIL 2 to PROBOIL.2X Upgrade Installation Guide v1b
10
2.1.4
Commissioning and testing
You have finished the installation, now please take a few moments to go through the commissioning and testing
process, this will ensure the product is working correctly, safely and to your satisfaction.
⚠
WARNING
:
You must not skip this section, we are not liable for any safety or performance issues as a result of
not following the step by step installation guide with due care.
1.
Turn on (open) fully the 98°C water handle.
⚠
After the air is purged from the system you
must
continue to run cold water through the tank for a further
minimum of a 5 minutes to flush it.
During the flushing period check all connections made during the installation carefully for leaks.
2.
After the flushing period is completed turn off (close) fully the 98°C water handle.
3.
Press and hold the
“
⏻
“
key on the boiler screen, it should switch to the standard screen and not display any error
“E”
codes.
4.
Press the
“+”
key on the boiler screen and set the target temperature to 98°C.
The boiler will take approximately
9 minutes
to reach its
“READY”
state. Use this time to complete the checklist
items in this guide.
The few first times the boiler fills and heats from a “fully cold” state it is normal that the tap may drip
slightly from the spout centre channel during heating, this will self-adjust with use.
5.
After the boiler reaches its
“READY”
state repeat steps 1-2.
6.
With all tap handles in the closed position again check the installation carefully again for any leaks.