Installation –
Electrical connection of the POLEMH6 |
23
12
Using the slotted screwdriver and a hammer, knock
out one of the pre-stamped M20 cable entries on
the top of the small distribution board.
13
Run the wallbox supply cable through the PG 13.5
cable gland to the terminal block in the small dis-
tribution board and secure the cable gland in the
cable entry.
This completes the installation of the wallbox on the mounting pole.
Electrical connection of the POLEMH6
The following section describes how to connect to the terminal block in the POLEMH6.
DANGER!
Dangerous electrical currents
Always observe the 5 safety rules:
1
Cut power source
2
Secure all cut-off devices
3
Verify absence of voltage
4
Ground and short-circuit
5
Cover or bar access to adjacent components under voltage
The supply cable must not be reconnected to the electricity grid until
Step 4
in this section!
Proceed as follows to connect the wallbox supply cable and the power supply cable to the terminal block of the
POLEMH6:
1
Shorten the wallbox supply cable to the required
length for connection to the terminal block in the
small distribution board.
Wallbox
House connection
L1 L1 L2 L2 L3 L3
N
N PE PE
2
Shorten the power supply cable to the required
length for connection to the terminal block in the
small distribution board.