7.4.3
Insert the wires for the smart meter communication
1. Remove the membrane (A) from the
EVSE.
2. Make a hole in the center of the
membrane.
3. Install the membrane.
4. If necessary, strip the cable to the correct
length. Refer to section
5. Push the wires through the membrane.
6. Put the cable (B) through the inlet hole.
7.4.4
Connect the wires for the smart meter communication
Connect the smart meter with ModBus RTU over RS485 to the EVSE.
Preliminary requirements
•
Slotted screw driver
•
Smart meter with ModBus
RTU interface
•
Wire for RS485. Refer to
. Obey the
local rules for the correct wire
insulation rating.
Procedure
1. Remove the plug (A) of the terminal
block (B) from the terminal block (B) of
the smart meter connection.
2. Connect the wires:
a. Connect the positive wire (C).
b. Connect the negative wire (D).
c. If the smart meter has an earthing
wire, connect the earthing wire (E).
3. Tighten the screws to the correct torque.
For the specification, refer to section
4. Install the plug on the terminal block.
7.4.5
Insert the Nano-SIM card
Preliminary requirements
•
A Nano-SIM card from the provider of the mobile network
A
B
A
B
C
D
E
Electrical installation
BCM.V3Y01.0-EN | 001
35